Circular No. |
Date |
Subject |
2025/CEDO/SD/01/FOB-BHADRAK |
09.05.2025 |
Temporary Condonation (upto 31.12.2026) of horizontal infringement (varies from 780mm to 1340mm) w.r.t IRSOD (BG) Revised, 2022, Schedule-I, Chapter-II, 7(b)(i) Note-(c) of existing FOB on PF-1 at Ch.72.50m F/CSB(RLJC end of BHC), Km: 293.289 F/HWH, in connection with due to yard remodeling at Bhadrak station of Khurda Road Division of East Coast Railway |
2024/CEDO/SD/05/NEW LALITPUR TOWN |
24.12.2024 |
NEW LALITPUR TOWN Station Yard – Sanction for Grade Condonation as per Note d(i) of Para 2, Chapter-II of Schedule-I of IRSOD (BG) 2022, for infringement of grade of 1 in 180 between km: 1043.810 and km: 1044.710 (LAR-KURJ line), 1 in 175 between km: 1043.097 and km: 1043.830 (DWA-BRRI line). 1 in 165 between km: 1043.830 and km: 1044.180 (DWA-BRRI line), 1 in 179 between km: 1044.180 and km: 1044.580 (DWA-BRRI line), 1 in 165 between km: 1043.097 and km: 1044.310 (LAR-BRRI line) and 1 in 179 between km: 1044.310 and km: 1044.710 (LAR-BRRI line) for a length of 900m, 733m, 350m, 400m. 1213m & 400m respectively in connection with construction of Dailwara – Bilari Chord Line in Jhansi Division of North Central Railway |
2024/CEDO/SD/04/SHIMILIGUDA
|
19.12.2024 |
SHIMILIGUDA Station Yard – Sanction for Grade Condonation as per Note d(i) of Para 2, Chapter-II of Schedule-I of IRSOD (BG) 2022 with ACS-02, for infringement of grade of 1 in 60.78 between Ch: 710m and Ch: 839m (UP line) and 1 in 60.15 between Ch: 703m and Ch: 839m (DN line) for proposed slip siding on KTV end for a length of 129m & 136m respectively in SHIMILIGUDA Station yard at KM. 93.123(F/KTV) in connection with proposed doubling between Kottavalasa-Koraput on Kottavalsa-Kirandul line in Waltair Division of East Coast Railway |
2024/CEDO/SD/03/BACHELI-1 in 80
|
19.12.2024 |
BACHELI Station Yard – Sanction for Grade Condonation as per Note d(i) of Para 2, Chapter-II of Schedule-I of IRSOD (BG) 2022 with ACS-02, for infringement of 1 in 80 grade between Ch: 825.5m and Ch: 2110.0 slip siding including Uniflow line takeoff point on KTV end for a length of 1284.5m in BACHELI Station yard at KM. 436.455(F/KTV) in connection with proposed doubling between Jagdalpur-Kirandul on Kottavalasa-Kirandul line in Waltair Division of East Coast Railway |
2018/CEDO/ORI/01 |
09.02.2024 |
Castle Rock- Kulem Stations – Relaxation to existing conditions for running Passenger/Goods trains in the Ghat Sections between Castle Rock – Kulem stations of Hubballi Division,SWR. |
2024/CEDO/SD/01/GHAZIPUR-1 in 102 |
07.02.2024 |
Ghazipur Ghat Station – Sanction for Grade Condonation as per Note d of Para 2, Chapter-II of Schedule-I of IRSOD (BG) 2022 with ACS-02, for infringement of 1 in 102 grade, between Ch: 0.579 km and Ch: 0.647 km, for 68.380m length, ( i.e. From Ch: 0.579 km to FM at Ch:0.597 Km and from FM to beyond 50m, i.e. up to Ch: 0.647 ) at Ghazipur Ghat station yard in connection with construction of Mau – Ghazipur-Tarighat new BG line in Varanasi Division of North Eastern Railway. |