Condonations to IRSOD - Other than Rolling Stock - 2006 |
File No.
|
Date
|
Subject
|
No.2005/CEDO/SD/4 |
06.1.06 |
Condonation of Infringing gradients.-Guntakal Division: Doubling of track between Guntakal–Hospet. Yard arrangements at Hagari Station |
No.2005/CEDO/SD/6 |
30.1.06 |
Condonation in extension of Circular Railway from Dum Dum Cantt. to NSCBIAirport |
No.2006/CEDO/SD/1 |
30.1.06 |
Condonation for adopting track centres less than 5300 mm, horizontal distance less than 2360 mm and vertical clearance less than 5870 mm in connection with junction arrangement work of Kanpur Central between Kanpur-Panki section of Allahabad division over NC Railway. |
No.2006/CEDO/SD/3 |
13.2.06 |
Condonation of infringement for lesser horizontal distance of transmission line tower/poles from the nearest track in construction of new siding for BPCL between Panki and Bhaupur station of Tundla – Kanpur section, Rajdhani route, Allahabad Division. |
No.2006/CEDO/SD/2 |
24.2.06 |
Guntakal Division: Doubling of track between Balapalle – Pullampet stations. Yard arrangements at Balapalle station. Condonation of infringing gradients. |
No.2006/CEDO/SD/4 |
31.3.06 |
Condonation to the infringements of grade of 1 in 272 which is steeper than 1 in 400 at Kotarlia station yard at Km. 576.10 from Howrah situated between Jamga and Raigarh stations. |
No.2006/CEDO/SD/5 |
04.5.06 |
Condonation for providing of fouling marks at 4265 mm at SAS Nagar (Mohali) Khara and New Morinda Yards on newly opened Chandigarh – Morinda railway line. |
No.2006/CEDO/SD/10 |
20.7.06 |
Electrification of Najibabad (incl)-Moradabad (excl.) BG section – Condonation of infringements due to Signal structures at Stations Najibabad, Murshadpur, Nagina, Habibwala, Sehora, Kanth, Matlabpur, Agwanpur & Harthala of Northern Railway. |
No.2006/CEDO/SD/6 |
21.7.06 |
Electrification of Kayankulam-Quilon-Trivandrum-Neman section- Condonation of infringments due to existing Engineering structures in the above section of Southern Railway. |
No.2006/CEDO/SD/9 |
21.7.06 |
Dindigul-Madurai section – provision of additional loop line at Ambaturai station (BG) – Condonation for lesser track spacing in the above section of S. Rly. |
No.2006/CEDO/SD/12 |
31.8.06 |
Condonation of infringements to Schedule of Dimension in implantation of signals on newly converted BG line on Delhi-Rewari section of Delhi Division of Northern Railway. |
No.2006/CEDO/SD/11 |
31.8.06 |
Approval to providing track centre 4.725 m on newly converted BG line on Delhi-Rewari section of Delhi Division of Northern Railway. |
No.2006/CEDO/SD/14 |
24.11.06 |
Condonation of infringement to the SOD (BG) revised, 2004 at ROB No.62-A between Bhogpur Sirwal and Cholang railway stations in connection with doubling of Bhogpur Sirwal and Tanda section of Firozpur Division of Northern Railway. |
No.2006/CEDO/SD/13 |
30.11.06 |
Electrification of Tirupati -Katpadi section - Condonation of infringements due to ROB already available at Chittoor station yard of Guntakal division of SC Railway.
|