Condonation to IRSOD - Other than Rolling Stocks - 2016
|
Circular No.
|
Date
|
Subject
|
2016/CEDO/SD/15 |
15.12.2016 |
Parichha - Condonation for lesser horizontal clearance of 32000mm (less than 38135mm, as per Pra 11(iv)(ii), Ch.-I, Sch.-I of IRSOD-2004 i.e. horizontal infringement of 6135mm), for tower of 220 kV power line crossing from centre of proposed new track between Parichha Terminal S Cabin – Railway stations in Jhansi – Bhimsen section of Jhansi Division of NCR. |
2016/CEDO/SD/35 |
18.11.2016 |
Mainpuri - Condonation for adoption of lesser track centre of 4725 mm (less than 5300mm, as per Para-I(ii), Chapter-II, Schedule-I of IRSOD-2004 i.e. infringement of 575mm), at the approaches of Mainpuri yard in C/W Etawah – Mainpuri new BG line of Allahabad Division of North Central Railway. |
2016/CEDO/SD/34 |
18.11.2016 |
Angar Station - Condonation for adoption of lesser horizontal distance from centre of track to any structure below rail level and up to formation level (less than 2360mm/2575mm as per Para 11(B) & its Note (c)/ Chapter-II/ Schedule-I IRSOD-2004, i.e. infringement of 85mm to 410mm) in Angar Station yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/32 |
18.11.2016 |
Vakav Station - Condonation for adoption of lesser horizontal distance from centre of track to any structure below rail level and up to formation level (less than 2360mm/2575mm as per Para 11(B) & its Note (c)/ Chapter-II/ Schedule-I –I IRSOD-2004, i.e. infringement of 160mm to 325mm) in Vakav Station yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/30 |
18.11.2016 |
Malikpeth Station - Condonation for adoption of lesser horizontal distance from centre of track to any structure below rail level and up to formation level (less than 2360mm/2575mm as per Para 11(B) & its Note (c)/ Chapter-II/ Schedule-I IRSOD-2004, i.e. infringement of 125mm to 450mm), in Malikpeth Station yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/28 |
18.11.2016 |
Madha Station - Condonation for adoption of lesser horizontal distance from centre of track to any structure below rail level and up to formation level (less than 2360mm/2575mm as per Para 11(B) & its Note (c)/ Chapter-II/ Schedule-I IRSOD-2004, i.e. infringement of 160mm to 375mm) regarding spacing of track centre in Madha Station yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/33 |
11.11.2016 |
Angar Station - Condonation for adoption of track centre of 5300mm which is in violation of Note (c)/Para 1(ii)/ Chapter-II/ Schedule-I to IRSOD regarding spacing of track centre in Angar Station yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway |
2016/CEDO/SD/24 |
11.11.2016 |
Condonation of infringement to IRSOD for lesser track centre of 4720mm (less than 5300mm; i.e. infringement of 580mm) from existing track line no. 1 (West Line) to new 5th Line from km. 1536/15A to km. 1535/3A in connection with provision of 5th and 6th lines between New Delhi and Tilak Bridge stations in Delhi Division of Northern Railway. |
2016/CEDO/SD/20 |
11.11.2016 |
Temporary condonation for the period of 24 months for infringing track centre of 4725mm (i.e. less than 5300mm) for laying of track to track centre at ROB no. 79A at km.571/7-8 between Hirakud – Godbhaga stations in connection with proposed doubling work of Sambalpur – Titagarh Doubling project of Sambalpur Division of East Coast Railway. |
2016/CEDO/SD/31 |
08.11.2016 |
Vakav Station - Condonation for adoption of track centre of 5300mm which is in violation of Note (c)/Para 1(ii)/ Chapter-II/ Schedule-I to IRSOD regarding spacing of track centre in Vakav Station yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/29 |
08.11.2016 |
Malikpeth Station - Condonation for adoption of track centre of 5300mm which is in violation of Note (c)/Para 1(ii)/ Chapter-II/ Schedule-I to IRSOD regarding spacing of track centre in Malikpeth Station yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/27 |
08.11.2016 |
Madha Station - Condonation for adoption of track centre of 5300mm which is in violation of Note (c)/Para 1(ii)/ Chapter-II/ Schedule-I to IRSOD regarding spacing of track centre in Madha Station yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/26 |
08.11.2016 |
Akalkot Road Station - Condonation for adoption of lesser horizontal distance from centre of track to any structure below rail level and up to formation level which is in violation of Para 11(B) & its Note (c)/ Chapter-II/ Schedule-I to IRSOD regarding spacing of track centre in Akalkot Road yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/25 |
08.11.2016 |
Akalkot Road Station - Condonation for adoption of track centre of 5300mm which is in violation of Note (c)/Para 1(ii)/ Chapter-II/ Schedule-I to IRSOD regarding spacing of track centre in Akalkot Road yard on Daund- Gulbarga Doubling project in Solapur Division of Central Railway. |
2016/CEDO/SD/23 |
08.11.2016 |
Temporary condonation up to 31.12.2016 for vertical infringement to IRSOD under Muniguda FOB pertaining to RE of Singapur Road – Titlagarh section of Sambhalapur Division in East Coast Railway. |
2016/CEDO/SD/21 |
08.11.2016 |
Condonation for infringing track centre varying from 4720mm to 5100mm (i.e. less than 5300mm) for tracks of existing DN Main Line (Proposed UP & DN main Line) and Proposed 3rd line (Proposed as DN Main Line) from km 572/26 to km 573/24 (i.e. from Ch: 572700.00m to Ch: 573609.00m) at Rayanapadu Station yard in connection with construction of 3rd B.G. electrified main line between Vijayawada – Kondapalli stations of Vijayawada Division in South Central Railway. |
2016/CEDO/SD/19 |
07.11.2016 |
Condonation for infringing track centre of 4725mm (i.e. less than 5300mm) for laying of track to track centre from km 1094.18 to km 1096.25 km (i.e. length of 2.07km) due to ROB at km 1095.104 between Guna-Mahugarha stations in connection with proposed doubling work of Guna-Ruthiyai (20.5km) section in Bhopal Division in West Central Railway. |
2016/CEDO/SD/17 |
07.11.2016 |
Condonation for horizontal infringement on LHS due to existing 400 KV (DC) over head power line crossing Km. 16/700-800 in Bengaluru City - Hassan section from centre of proposed new BG line track of Bengaluru Division of S.W. Railway. |
2016/CEDO/SD/22 |
01.11.2016 |
Temporary Condonation for five (05) years for horizontal infringement of IRSOD on RHS due to existing 400 KV (DC) over head power line crossing Km. 39/17-18 in Haridwar – Dehradun (under electrification) section of Moradabad Division of Northern Railway. |
2016/CEDO/SD/16 |
14.10.2016 |
Temporary Condonation up to 31th December 2016 for infringing Vertical infringement (less vertical clearance from rail level) of lowest conductor of 132 KV transmission line between Kadipur – Sarnath station (km. 194/7-8) in connection with Doubling work of Varanasi Division of North Eastern Railway |
2015/CEDO/SD/14 |
12.08.2016 |
Daund yard – proposal for condonation for infringement regarding change of gradient within 30 mts. of points and crossings in the existing yard which is in violation of Chapter – II Item No.2 (e) (2) of IRSOD in connection with provision of Tower Wagon Siding in place of track machine siding and a new track machine siding and also dismantling of Down Reception line No.6. |
2016/CEDO/SD/11(Duplicate) |
29.07.2016 |
Temporary Condonation upto 05 years, for infringing Vertical & Horizontal clearances under Road Over Bridge no. 12 (Km.- 13/6-7) at Noadardhal in connection with introduction of new electrification of 25 KV (AC) under Khana - Rampurhat section of Howrah Division of Eastern Railway. |
2016/CEDO/SD/14 |
12.07.2016 |
Dharwad Yard : Condonation for (i) adoption of steeper gradient of 1 in 100 between km. 489.357 to km. 489.979 & between km. 487.542 to km. 487.974 and (ii) provision of lesser track centre of 4720mm between km. 487.522 to km. 487.882 at ROB no. 232; in connection with “Doubling of track between Hospet – Tinaighat section” in Dharwad Station Yard of Hubli Division of South Western Railway. |
2016/CEDO/SD/13 |
18.07.2016 |
Devarayi Yard : Condonation for adoption of steeper gradient of 1 in 103 between km. 545.300 to km. 547.320 (2020m length) in connection with “Doubling of track between Hospet – Tinaighat section” in Devarayi Station Yard of Hubli Division of South Western Railway. |
2016/CEDO/SD/12 |
12.07.2016 |
Temporary Condonation upto September-2017, for infringing Vertical & Horizontal clearances under Foot Over Bridge (Km.- 70/8-9) at Sainthia in connection with introduction of new electrification of 25 KV (AC) under Khana – Rampurhat - Pakur section of Howrah Division of Eastern Railway. |
2016/CEDO/SD/10 |
12.07.2016 |
Temporary Condonation for infringing Vertical & Horizontal clearances under Road Over Bridge no. 122 (Km.- 70/5-6) at Sainthia in connection with introduction of new electrification of 25 KV (AC) under Khana - Rampurhat section of Howrah Division of Eastern Railway, for 05 years. |
2016/CEDO/SD/09 |
22.06.2016 |
Temporary Condonation for infringing Horizontal Clearances of Extra High Tension (132 KV and 220KV) Power Line Crossings in between Khana & Jhapterdhal stations in connection with introduction of new electrification of 25 KV (AC) under Khana-Pakur section of Howrah Division of Eastern Railway, upto March, 2017 |
2016/CEDO/SD/08 |
31.05.2016 |
Parasia Yard : Condonation for retention of existing gradient of 1 in 100 between km. 960.565 to km. 960.771 (206m length) in Parasia Station in connection with “provision of Tower Wagon siding (electrification of Amla-Chhindwara line), Central Panel (route setting type)alongwith Multi Aspect Colour Lighting Signalling(MACLS), increasing the CSR to accommodate full rake freight train and provision of simultaneous reception of trains” in Parasia Station Yard of Nagpur Division of Central Railway.
|
2015/CEDO/SD/16 |
12.05.2016 |
Condonation of infringement in respect to horizontal and vertical clearance of Fly-over (Bridge no. SK-4) at Km. 273/7-9 w.r.t. IRSOD for proposed third line and for UP & DN lines in between Gamharia – Sini Stations in Tatanagar – Chakradharpur section of Chakradharpur Division of South Eastern Railway. |
2016/CEDO/SD/07 |
12.05.2016 |
Urkura Yard : Condonation for gradient of 1 in 154.15 in Urkura Station (Raipur – Urkura; from Ch: 39.26m to Ch: 448.78m) in connection with Yard Remodelling of 3rd Line at Urkura Station Yard of Raipur Division in South East Central Railway. |
2016/CEDO/SD/03 |
21.04.2016 |
Indore Yard : Condonation for infringing vertical Clearances for existing ROB (Shastri Bridge) at CH: 326.95 at Indore yard (Ratlam end) regarding Gauge Conversion project of Ratlam-Mhow-Khandwa—Akola with the introduction of 25 KV AC Traction between Laxmibainagar-Indore section in Ratlam Division in Western Railway. |
2016/CEDO/SD/02 |
21.04.2016 |
Indore Yard : Condonation for infringing vertical Clearances for existing ROB (Shastri Bridge) at CH: 326.95 at Indore yard (Ratlam end) regarding Gauge Conversion project of Ratlam-Mhow-Khandwa—Akola with the introduction of 25 KV AC Traction between Laxmibainagar-Indore section in Ratlam Division in Western Railway. |
2016/CEDO/SD/06 |
18.03.2016 |
Condonation of infringements for adoption of lesser horizontal clearances from centre of track to any structure with respect to IRSOD-2004 regarding existing 20 nos. Transmission line towers of EHT power line crossing in CSTM-Panvel Harbour line and Thane-Vashi/Narul Trans-Harbour line section in connection with modification of existing 1500 Volts DC traction to 25 KV AC traction in Mumbai Division of Central Railway. |
2016/CEDO/SD/05 |
18.03.2016 |
Condonation of infringements for adoption of lesser vertical clearances from rail level to underside of ROB & FOB with respect to IRSOD-2004 regarding existing 02 nos. ROBs and 02 nos. FOBs in CSTM-Panvel Harbour line and Thane-Vashi/Narul Trans-Harbour line section in connection with modification of existing 1500 Volts DC traction to 25 KV AC traction in Mumbai Division of Central Railway. |
2015/CEDO/SD/18 |
25.02.2016 |
Bangalore Division : Condonation for infringing Horizontal Clearances of Over Head 66 KV and 220KV Power Line Crossings regarding Electrification of Bangalore City- Kengeri Section on Bangalore Division in South Western Railway. |
2016/CEDO/SD/01 |
24.02.2016 |
Palghat Division : Condonation for infringing vertical Clearances for existing ROB no. 977 B at Km. 664/900-665/0 at Kozihikode yard regarding introduction of 25 KV AC Traction in the Shoranur – Mangalore – Panambur Section in Palghat Division in Southern Railway. |
2015/CEDO/SD/19 |
20.01.2016 |
Guntakal Division : Condonation for infringing vertical Clearances for existing ROB at Ananthapur Station regarding introduction of 25 KV AC Traction in the Gooty - Dharmavaram |