CHAPTER VI
INVESTMENT PLANNING AND WORKS BUDGET
Investment Planning and Works Programme Section
601
|
Investment Planning and Works Programme - General |
603
|
Advance Planning |
607
|
Scrutiny of Schemes before preparation of
Preliminary Works Programme |
609
|
Preparation of Preliminary
Works Programme |
622
|
Integrated Budget |
623 |
Final Works Programme |
624
|
Works
Budget |
625
|
Demand for Works Grant |
626
|
Financing of Works Budget |
628
|
Distribution of Funds by Railway Board |
632
|
General Rules on Budget |
633.
|
Planning for Survey |
General
601.
Investment decisions relating to the creation, acquisition and replacement of assets on
the Railways are processed through the annual "Work, Machinery and Rolling Stock Programme".
Instructions regarding the preparation of the Machinery and Rolling Stock Programme are contained in
Chapter XV of the Indian Railway Code of Mechanical Department (Work shops). On the basis of the estimate
of the Plan funds requirement for the ensuing year, the Railway Board lay down the financial limits (see
para 609) under various plan heads (refer to Appendix I) within which the Railway Administrations are
required to make out their programme for the following years duly vetted by the Financial Advisor and Chief
Accounts Officer for submission to the Railway Board by a specified date. The programmes are
examined by the Railway Board and discussed, where necessary, with the General Managers and the works to
be undertaken as well as the outlays during the Budget year are decided upon.
602. The various stages of investment planning and preparation of the Final Works Programme
are given below :
- (i) Formulation of schemes as a part of advance planning;
- (ii) Submission of major schemes for advance scrutiny and clearance by the
Railway Board for selection of Projects to be taken up in the following year.
- (iii) Preparation of the Preliminary Works Programme within the financial ceiling laid
down by the Railway Board ; and
- (iv) Discussions with the Railway Board and submission of the Final Works Programme.
The investment planning process through the above stages is dealt with in the
following paragraphs :-
Advance Planning
603. The preparation of the annual Works Programme of a Railway is not an isolated exercise
for the year, but is part of a continuous planning process from the level of the Divisional Officer
upwards. Investment proposals emanating from the Division would be those which are intended to effect
improvement in operation or remove bottlenecks etc., within the Division itself. Major investment proposals
which benefit a Zonal Railway System or the Indian Railway as whole should be co-ordinated and planned at
the level of the Railway Headquarters or the Railway Board, where necessary.
604. An important requirement for effective investment planning is the realistic estimation of
project costs. Full details of the scheme must be worked out and no scheme should be included in the
Railway's Works Programme unless detailed plans and estimates have been prepared and are ready.
Detailed Traffic and Engineering surveys should be carried out for new lines, gauge conversions doublings and
for other line capacity works costing more than Rupees Five Crores each. In the case of yard
remodellings, line capacity works i. e., goods shed facilities and important buildings the estimates should be based
on plans approved and signed by the concerned departments who should scrutinize the plans carefully
to avoid the need for making any substantial modifications in the required facility at a subsequent stage.
If major changes in the plans/schemes/specifications of works nevertheless become necessary
and are likely to lead to substantial excesses over the sanctioned estimates the changes asked for by
the concerned departments should not be agreed to unless reviewed and approved by the competent
authority sanctioning the original estimate. In regard to proposals for new marshalling yards goods
terminals, and tranship yards etc., work study teams should go into the actual working before formulating
schemes for the additional facilities required.
605. It is an essential feature of the railway system as a commercial undertaking that
expenditure, other than that wholly chargeable to ordinary Revenue, incurred on new assets or for improvement
of existing assets should be financially justified before it is incurred. Detailed instructions regarding the
financial appraisal of Railway projects are contained in Chapter II of the Indian Railway Financial Code to
which reference may be made. The cases where no financial justification need be given are contained in
para 202 of the Indian Railway Financial Code. Detailed financial implications (including financial return)
should be worked out in all cases including works financed from Development Fund, Accident
Compensation, Safety and Passenger Amenities Fund or Open Line Works Revenue (see para 626). If the
prescribed return is found to be not obtainable on the anticipated level of traffic, the Railway Administration
should examine whether the proposal cannot be reduced in scop, or given up in favour of some other
alternative, or postponed until traffic prospects improve.
606. When a number of works have to be carried out to achieve a common objective, the
financial implications or justification should be worked out for the entire scheme as a whole. In case where the
wider schemes covers two railway, a joint estimate of cost should be prepared for the Railway Board's
consideration. The Railway in which the major portion of the work falls should obtain figures from the
contiguous Railway for submitting joint figures of cost and financial implication to the Railway Board.
Scrutiny of Schemes before preparation of Preliminary Works Programme
607.
All schemes costing Rs. 20 lakhs or above should be worked out comprehensively and sent
to the Board along with full details of (i) the technical features, (ii) Cost break-up. (iii) benefit expected
to accrue and (iv) financial implications. A sketch map of each proposal should also be sent. The
Railway Administration must clearly bring out the purpose of each scheme and confirm that the proposal meets
the objective fully and that the scope and cost of the project have been arrived at after the fullest
possible investigation including assessment of the financial implications. After the schemes have been
scrutinized by the Board, the Railway Administrations should be advised of the acceptance, with or without
any modifications for inclusion in the Works programme.
608. Track renewal proposals costing Rs. 20 lakhs and above are initially scrutinised by the
Board, keeping in view the availability of permanent way materials, progress of the works already sanctioned
and other technical factors. For this purpose the Railway Administrations should send all track renewal
proposals costing Rs. 20 lakhs and above together with technical data like traffic density, age, conditions of
track components etc., in the form prescribed by the Board to reach the Boards office by the stipulate date.
After the proposals are screened by the Board, guidelines are issued to the Railway Administrations to
reframe their proposals for inclusion in the Works Programme.
Preparation of the Preliminary Works Programme
609. The Chief Engineer of the Railway will be primarily responsible for ensuring that the
proposals prepared by the various departments are complete in all respects and are correctly prepared. The
overall priorities within the ceilings given by the Board will also be fixed by him in consultation with the
General Manager and other Heads of Departments. He will be responsible for the preparation and timely
submission of the Preliminary and the Final Works Programme.
610. In or about June/July each year the Railway Board should convey to each Railway, in
respect of each Plan Head, the total outlay within which the Works Programme should be framed by the
Railway. A list of the Plan Heads is given in Annexure I. On receipt of this financial ceiling the Railway
administrations should take stock of the schemes already formulated and those under consideration and select
for inclusion in the Works programme within the financial ceiling such works as are expected to yield
the maximum benefit to the Railway, preference being given to works in progress. Further necessary
changes in the investment schedule may be made in order to work within the financial ceiling for the year
such modifications being taken note of in framing the preliminary Works Programme and revising the
financial implications, if necessary.
611. The Preliminary Works Programme for the following year should be submitted by the
Railways to the Railway Board by 1st week of September or such earlier date as may be laid down by the
Board. Proper financial appraisal of each work should be given in the Preliminary Works Programme
together with the comments of the Financial adviser and Chief Accounts Officer.
612. The project cost should be based on firm data both as to quantity and rates at current
price levels, and should any increase occur in prices during the period intervening between the initial
preparation of the project estimate and its inclusion in the works Programme, the estimate should be
updated taking into account any significant changes in the wages and material prices as well as increase in
freights and fares. No other increase such as on account of change in scope of the project should be
allowed without prior reasons being adduced for acceptance by the Railway Board. A sketch showing the
proposal should accompany each proposal.
613. Each investment proposal should be accompanied by a detailed plan showing the
scheduling of the project to match the traffic requirements and the financial outlay proposed for the year should be
in accordance with this project schedule to enable the Railway Board to arrange for a realistic funds
allocation for implementation of the programme.
614. In deciding the outlays for the various works Railway Administrations must endeavour to
progress all works in progress speedily and bring them into use at the earliest possible date. A work which has
been sanctioned and for which funds have been allotted whether in the original or supplementary budget of
a year should be treated as a "work in progress" for the next year and provided for as such in the
programme. Such works should be grouped as indicated in para 619.
615. The Railway Administrations should make a realistic assessment of the amount required
for each work in progress and necessary provision should be made for it in the Works Programme. In
estimating the provision for works during the budget year a generous allowance should be made for those
delays in execution which though unforseen are known from experience to be so liable to arise particularly prior
to inception and during the initial stages of large projects. The provision made should take into
account adjustment of charges on surveys connected with a project.
616. In exhibiting the
outlay for the current year against individual works in the works programme, the
outlay should be as per Pink Book, and in exceptional cases where the Railways
propose any substantial increase in the outlay with corresponding reductions
against other works, such revised outlay may be shown separately in brackets
below the outlay as furnished in the Pink Book duly explaining the reasons for
doing so in footnotes at the appropriate places. As far as possible only the
last sanctioned costs should be exhibited. Wherever it is visualised that the
cost would involve an excess over the last sanctioned cost, effective steps
should be taken well in time to have the revised estimate prepared and
sanctioned by the competent authority before the Works Programme is sent to the
Board. In case where the revised estimates are sanctioned subsequent to the
despatch of the final Works Programme but before the end of January of the
following years the same should be promptly advise to the Board to enable to the
latest sanctioned cost being exhibited in the Pink Book to be circulated
alongwith the Budget. In all case of revised costs sanctioned by the Board,
reference to the letter of sanction should invariably be indicated.
617.
Works once introduced through a Works Programme
(including Track Renewal Programme) and taken up after the estimates have been
sanctioned by the competent authority should continue to be included every year
till they are finally completed, except in case where the works have reached the
completion stage and where funds required if meagre could be found by
reappropriation.
618.
The Works Programme is compiled in the following
format :-
Form E. 618
WORKS PROGRAMME 1975-76
Demand No...............................
Figures in
thousands of rupees)
Item No. |
Authority |
Particularsof
Works |
Cost |
Expenditure
to end of 3/74 |
Outlay for |
Balance |
1974-75 |
1975-76 |
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
|
|
|
|
|
|
|
|
Note :--Years have been shown in the form for the
purpose of illustration.
In respect of "Works in Progress" reference to item
No. of the current years Pink Book and also the authority under which the
work was first started should be indicated. The works should be arranged as per
the Plan Heads.
619.
The items in the Works Programme should be
grouped under the following categories while compiling the Works Programmes :--
620. The works are
further made into sub-groups of
(i) Works costing more than Rupees Five
Lakhs each and (ii) Works costing upto Rupees Five lakhs each. Under (ii) works costing upto Rupees two
lakhs each in the case of Track Renewal works and for works costing upto Rupees one lakh each in the case
of other works only lumpsum provision should be shown without detailing individual works. Within each
sub-group, the works are presented under each Plan Head.
621. A map showing the Railway System and indicating the new lines, doublings, major
yard remodellings, important line capacity and signalling works which are in progress as well as
proposed should be attached to the Works Programme. An alphabetical index of works and various
managerial information regarding critical materials, expenditure position relating to passengers and railways
users amenities etc. which will be prescribed by Railway Board should be included.
622. Integrated
Budget.-The Annual Budget of Railways consists of assessment of earnings
and expenditure forming part of Revenu Budget, and that relating to the investment decisions taken
through the Works Machinery and Rolling Stock Programmes. In order to co-relate the decisions relating to
all these aspects, a consolidated budget called integrated Budget including Revenue Budget,
Works Programme and the Machinery and Rolling Stock Programmes should be submitted by the
Railways alongwith the preliminary Works Programme. The Integrated Budget will include the projections of
traffic and earnings, works working expenses, the estimated financial results for the ensuing year, and
the operating ratio in the proforma specified by the Railway Board. The Railways
should also furnish the
details of Rolling Stock required on replacement account and addition account, duly co-relating it to the
anticipated increase in traffic. In the covering note to the Intergrated Budget the Railways should bring out the effect
of the budget proposals on the efficiency of operations as indicated by the operating ratio and the
financial viability of the system as reveraled by the financial returns on cpaital investment. After discussion of
the Preliminary Works Programme, a revised Integrated Budget should be submitted along with the
Final works Programme duly taking into account the changes that might have taken place in the
meanitime.
The Integrated annual budget may be prepared under the personal guidance of the General Manager and
with the assistance of Financial Adviser and Chief Accounts Officer.
Final Works Programme
623. After having examined the individual Railways Programme, and discussions with the
General Managers, the Railway Board will decide the works which should be undertaken during the following
year and which should be included in the Final Works Programme. The Railway Administration gives will
then modify their Works Programmes as a result of the Board's decision and send their Final Works
Programme to the Railway Board by the stipulated date.
Section II-Works Budget
624. Works
Budget.--The revised and budget estimets for the construction, acquisition
and replacement of assets are briefly known as Works Budget. The revised estimate gives an estimate
of funds required for the current year and the budget estimate referes to the following year. For a
detailed study of the Railway Budget, Chapter III of the Indian Railway Financial Code should be refered to.
The budget estimate for the works are based on the Works Programme approved by the Board.
The requirement of funds both for new investments and for works in progress are submitted in the form
of "Demand for Grants" in the Works Machinery and Rollings Stock Programme which forms a part of
the Budget papers presented to the Parliament. While compiling the Works Machinery and Rolling
Stock Programme for presentation in the Parliament only works costing Rupees five lakhs and above are itemised.
Demand for Works Grants
625. The proposal of Government in respect of sums required to meet the expenditure from
the Consolidated Fund of India are to be submitted in the form of Demands for Grants to the
Parilament.
The Demand shall be for gross expenditure, the credits or recoveries (refer to para 335 of Indian
Railway Financial Code) being shown in the form of footnotes to Demands.
The Demand for Grants for the Works Budget is :
Demand No. 16 : Assets-Acquisitions, Construction and Replacements.
Financing of Works Budget
626. Works chargeable to Demand No
16.Assets-Acquisitions Construction and
Replacements are financed from railway revenue when it is charged to OLWR or financed from Capital.
Depreciation Reserve Fund, Development Fund, Accident Compensation Safety and Passenger Amenities
Fund. Expenditure budgetted under "capital" involves increase in the Capital-at-charge of the Railways
and hence is the liability for payment of dividend to General Revenue subject to the relief/exemptions
granted by the Convention Committee. "Works expenditure" of the Railway is thus financed from Revenue,
Railway Funds and Capital provided by the General Revenues. The Railway Funds are Depreciation
Reserve Fund, Development Fund and Accident Compensation Safety and Passenger Amenities Fund. For
Details regarding the operation of the funds, reference may be made to Chapter. III of the Indian Railway
Financial Code. In the event of the railways revenue surplus not being adequate to fully meet the requirements
of Development Fund Expenditure, the budgetary support from the General Revenues would also
include temporary loans to finance expenditure from the Development Fund. The expenditure under works
Budget of the Railways is, therefore, determined by the resource allocation under various Plan Heads.
627. Credits or
Recoveries. There are certain credits or recoveries which are excluded from
the scope of the Demands presented for vote of Parliament, (refer to para 335 of Indian Railway
Financial Code for details). Though these credits or recoveries are outside the scope of the Grants, they
are booked in accounts as reduction of expenditure, e.g. credit for released materials. A list of credits
or recoveries which should be excluded from the scope of the Demand should be sent in Form 335F
along with the revised estimates of the current year and budget estimates of the ensuing year under
each Demand.
628. Distribution of Funds by the Railway
Board. The Grants as voted by the Parliament
and the appropriations for charged expenditure (for details of `voted' and' charged' expenditure reference
may be made to paras 302 and 303 of the Indian Railway Financial Code) as sanctioned by the President
are distributed by the Railway Board among the Railway Administrations and other authorities, subordinate
to them as soon as possible after the Budget is sanctioned. The sums so distributed are called
"Allotments" and the orders by means of which the allotments are made are called "Budget Orders". The
allotments made out of funds voted by the Parliament are shown as "Voted" and those fixed by the President
are shown as "Charged".
629. The Budget Orders are accompanied by the final issues of "Demands of Grants" and
"Works Machinery and Rolling Stock Programmes", containing the detailed distribution of the Budget
allotment made to railway administrations for working expenses and Capital, Depreciation Fund, Development
Fund, Open Line Works (Revenue) and Accident Compensation, Safety and Passenger Amenities
Fund expenditure. The Budget allotment made to railway administration is intended to cover all charges
including the liabilities for past years to be paid during the year or to be adjusted in the accounts for it. It shall
be operative until the close of the financial year. Any unspent balance shall lapse and shall not be
available for utilisation in the following year.
630. In the event of the Budget Orders of the Railway Board not being received before
the commencement of the financial year, the railway administrations are empowered to incur
expenditure pending the receipt of the Budget Order on works which were in progress at the end of the
previous financial year. All expenditure incurred under this must be treated as a charge against the
allotments eventually made for such works.
631. When the Budget Orders issued by the Railway Board show any reduction in the
estimate originally submitted to them, prompt measures should be taken by the railway administrations to limit
the expenditure to the amounts allotted and distributed by the Railway Board.
General Rules on Budget
632. The general rules on Railway Budget are contained in Chapter III of the Indian Railway
Financial Code to which reference may be made.
633.
Planning for Surveys. As surveys for the initial step of investment planning, the
programme of surveys requires to be planned in advance and reviewed along with the investment decisions
being taken in the annual Works Programme meeting being held in Railway Board Office. A separate
statement indicating the surveys in progress and the new surveys proposed to be undertaken should be
prepared and included in the Railway Works Programme being submitted to the Railway Board. The need for
each survey should be clearly stated bringing out inter alia whether the same survey was proposed earlier
and if so with what results.
634. The cost of surveys or preliminary investigations to examine the feasibility and prospects
of new line constructions and other projects is charged to Demand No. 2 which is a Revenue Demand.
All surveys costing more than Rs. 1 lakh require prior approval of Parliament. If the construction of a
project is undertaken, the expenditure on the Survey is transferred to Capital or other appropriate heads
by Credits to Revenue, irrespective of the year in which the expenditure was originally incurred. The
charges on surveys are mostly made up of the pay and allowances of staff, cost of transport, cost of
mathematical and other instruments and camp and office equipage. The allowance for depreciation on materials
likely to be left over on completion of the surveys should be made on a scale justified by past experience.
The Budget estimate of surveys should provide for any adjustments necessary under the rules in respect
of surveys pertaining to a project the construction of which has been or is to be taken in hand. The
revised estimates of surveys for a year and the budget estimates for the ensuing year based on the
decisions arrived at in the Works Programme meeting should be prepared in respect of each survey in the
following form and submitted in duplicate so as to reach the Railway Board not later than 1st December of the
year to which the ""revised estimates" relate.
FORM NO. E-633
Demand
No. 2-RAILWAYS (SURVEYS)
..............
RAILWAY
REVISED ESTIMATES
FOR (1975-76) AND BUDGET ESTIMATE FOR (1976-77)
(To be despatched
so as to reach the Railway Board by the 1st December, 1975 without
fail)
(Figures in thousands of rupees)
Particulars
|
Total
estimated or sanctioned cost
|
Expenditure
to end of 1973-74
|
Expendi-ture
for 1974-75
|
Budget
Estimate 1975-76
|
Revised
Estimate 1975-76
|
Budget
Estimate 1976-77
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
Total
.
Deduct.-
Credits for write back to Capital Account of expenditure on the
following surveys.
Net
|
|
|
|
|
|
|
Note.-Years have
been shown in the form for purposes of illustration.
**********
|