CHAPTER II
MODES OF INVESTIGATION OF RAILWAY PROJECTS
201 |
Project Development Process
|
202 |
Feasibility Studies |
203 |
Techno Economic Survey
|
204 |
Classification of Surveys
|
205 |
Decision to undertake Survey
|
206 |
Preliminary Investigation
|
209 |
Terms of Reference
|
210 |
Categories of lines
|
214 |
scope of Survey Operations
|
215 |
alignment
|
216 |
Position of Curves
|
217 |
Degree of Curvature
|
218 |
Transition Curves
|
220 |
Gradients
|
221 |
Vertical Curves |
222 |
Alternative alignments
|
223 |
Plane Table Survey
|
224 |
RiversImportant Rivers
|
226 |
High Flood Levels
|
227 |
Diversion of rivers
|
228 |
Protection Works |
229 |
Construction of new railway bridges
|
230 |
Provision of traction over head equipment structures on
new bridges
|
231 |
Station Sites
|
233 |
Junction Arrangements
|
234 |
Survey for the provision of additional lines
|
237 |
Gauge Conversion Surveys
|
243 |
Railway Electrification Surveys
|
249 |
Field Books
|
250 |
Notes to be made in the field
|
251 |
The Operations of a Reconnaissance Survey
|
253 |
General Instructions
Notification in Local Gazette
|
254 |
Damage to property and Trespass
|
255 |
Compensation for damage
|
256 |
Religious edifices etc.
|
257 |
Interference with pre-existing Railways, Roads, Canals
etc |
259 |
Military Requirements
|
267 |
Quarterly Progress Report |
268 |
Feasibility Studies |
201. Project Development
Process. The Project Development Process consists of the
following sequences :
-
(i) Assessment of future needs/requirements;
-
(ii) Project formulation, which is to determine the various options to meet the demand;
-
(iii) Project investigation which is to examine some selected alternatives as defined in the terms
of reference to the Project Investigator and preparation of Techno Economic Survey Reports
(cf. Para 203) or Feasibility Reports (cf. Para 202) as the case may be;
-
(iv) Project evaluation which may involve economic analysis, (cf. Para 235-F) or Social Profitability
Analysis, in addition to financial appraisal;
-
(v) Selection of a scheme based on such an appraisal; &
-
(vi) Further detailed examination of the selected scheme by conducting a Preliminary survey (cf.
Para 204) wherever necessary for accurate costing and preparation of projects reports (cf.
Para 502) and investment decisions.
202. Project formulation is an essential part of the planning process and the Project
Investigator must be given clear indications regarding the objectives to be achieved and the options to be investigated.
Preinvestment decision investigations may relate to long term planning and to decide priorities.
Such investigations are in the form of Reconnaissance Surveys (cf. Para 204) where much detailed
investigations are not carried out and cost estimation will also be approximate. Investigations of this nature are
termed "Feasibility Studies".
203. Techno-Economic Surveys. Pre-investment decision investigations may also
involve examination of various alternatives including optimisation of existing facilities to decide the best
alternative from financial and operating point of view to make an ideal investment decision. Such
investigations relating to new lines, doublings, gauge, conversions schemes, yard remodellings, passenger terminal
etc. involving Preliminary Engineering-cum-Traffic Surveys, (cf Para 204) are termed as
Techno-Economic, Surveys. In these surveys, data, regarding the growth of traffic is collected, traffic projections are
made the existing facilities are evaluated the possibility of optimising them and new alternative schemes
are examined. An estimate prepared based on such an investigation should under ordinary circumstances
be sufficiently accurate to permit investment decision being taken."
204. Classification of
Surveys. The various kinds of Surveys which are carried out as a
part of investigation of Railway projects are indicated below :
(i) Traffic
Surveys. This is a detailed study to make a forecast of the traffic prospects to
facilitate the projection of the most promising route and the category of line (cf. Para 210 and
211) to be constructed in the case of new lines and to assess the quantum of traffic to
determine the traffic facilities to be provided on an existing line. These surveys are to be
under-taken in conjunction with Reconnaissance or Preliminary Engineering surveys so that
the Technical feasibility and costs of the alternative proposals can be taken into account
while formulating the recommendations.
(ii) Reconnaissance Survey :
-
(a) This term should apply to all rough and rapid investigations of an area with a view to
determine the technical feasibility and approximate cost of one or more routes for a projected
Railway line from a general examination with the help of contoured Survey of India maps
and other available material without a more careful investigation of the field and with the use
of only those instruments that will repidly give approximate distances and heights such as
prismatic compass, clinometer and similar instruments.
-
(b) Where suitable aerial Photographs are available, field investigations by instruments can be
considerably avoided/dispensed with by Steroscopic studies of the Photographs and
site inspections as may be required.
(iii) Preliminary Survey :
(a) This consists of a detailed instrumental examination of the rout / or routes selected as
a result of "Reconnaissance" in order to obtain a close estimate of the probable cost of the
projected line, under this survey. However, staking out of the alignment with a theodolite is
not required. Whether a line is to be built or not will usually be decided on the result of the
survey considered in conjunction with Traffic survey. The Railway Board may, however,
require the submission of an estimate based on Final Location Survey before
sanctioning the commencement of construction.
(b) Whether suitable aerial photographs are available, detailed instrumental examinations
of the route/ routes selected as a result of "Reconnaissance Survey" could be
considerably avoided dispensed with by using photogrammetric methods which involve
plotting of contoured strip maps.
From aerial Photographs on 1: 10,000 scale or 5 times the scale of the available photographs
for obtaining an optimum alignment.
(iv) A Final Location Survey will generally be a post investment decision investigation to
prepare working details and to make accurate costing in certain cases. The principal
differences between the work required in a Final Location Survey and that in a
Preliminary Survey is that the alignment finally selected during a survey should be
fully staked on the ground with a theodolite and/or
Electronic Distance Measuring
Instruments, the report should be fuller and detailed plans and sections should be
submitted.
205. Decision to Undertake Survey.-Railway Administration have no power to
undertake Surveys on their own. After a Survey is included in the sanctioned Budget the General Managers
can sanction Survey Estimates costing upto Rs. 3 lakhs.
206. Preliminary Investigation.-In the case of construction of new lines a
preliminary investigation should be undertaken by the Railway Administration concerned to determine how the
proposed line will fit in with the general scheme of future railway development. The preliminary investigation
should be based on a careful study of information already available from existing maps, published figures of
trade and population of the area to be served and financial and statistical data of existing railways in
similar country.
207. Form the results of this investigation it should be possible for the Railway
Administration to decide the surveys (see para 204) to be undertaken and take a preliminary view of the category of
line (see para 210 & 211) to be provided.
208. If it is decided to undertake a Survey in connection with any proposal for the
construction of a new line, additional lines and gauge conversion, estimate for the proposed Survey should be
prepared. In the case of Surveys for new lines, the information collected in the course of Preliminary
Investigation (vide para 206) should be embodied in the report accompanying the estimate.
209. Terms of Reference.-The project Investigator should be supplied by the
Railway Administration with terms of reference, and should indicate the category of line, ruling gradient to
be adopted etc. The terms of reference should include instructions regarding the scope and nature of
the investigations to be carried out, particulars of any railway lines already projected in the area and
what undertakings or interests, if any, are involved in the proposal. The terms of reference should also
include instructions to the officer-in-charge of the survey to visit the headquarters of the Railway Administration
at suitable intervals both during the progress of work in the field and during the period of recess in order
to consult the General Manager and his principal officers and where necessary have the original terms
of reference modified from time to time.
210. Categories of Lines.-Broad Gauge lines on Indian Railways are classified into
various categories indicated below, on the basis of future maximum permissible speed.
(1) Group
`A'-For a sanctioned speed of 160 km. per hour
The minimum rail section to be adopted will be 60 Kg. in section having traffic density of over
20 GMT and 52 Kgs in other sections.
The minimum sleeper density shall be 1,660 numbers per Km.
The ballast cushion shall be 30 cm.
Bridges will be built to revised BG loading of 1975 with a maximum axle load of 22.5 tonnes
for the locomotive and train load of 7.67 tonnes per meter behind the locomotives with a maximum axle
load of 22.9 tonnes for the train load.
(2) Group
`B'-For a sanctioned speed of 130 km. per hour
-
The minimum rail section to be adopted will be 60 Kg. in sections having traffic density of over
20 GMT and 52 Kg. in other sections.
-
The minimum sleeper density shall be M+7.
-
The ballast cushion shall be 25 cm.
Bridges will be built to revised BG loading of 1975 with a maximum axle load of 22.5 tonnes
for the locomotive and a train load of 7.67 tonnes per metre behind the locomotives with a maximum axle
load of 22.9 tonnes for the train load.
(3) Group
`C'-Suburban Sections.
-
The minimum rail section to be adopted will be 60 Kg. in sections having traffic density of over
20 GMT and 52 Kg. in other sections.
-
The minimum sleeper density shall be M + 7.
-
The ballast cushion shall be 25 cm.
Bridges will be built to revised BG loading of 1975 with a maximum axle load of 22.5 tonnes
and a train load of 7.67 tonnes per metre behind the locomotives with a maximum axle load of 22.9 tonnes for
the train load.
(4) Group
`D'-Where the maximum sanctioned speed is 100 Kms/hour, as at present.
-
The minimum rail section to be adopted will be 60 Kg in sections having traffic density of over
20 GMT, 52 Kg. in sections having traffic density from 10 to 20 GMT and 44.5 Kg in sections having
traffic density of less than 10 GMT.
-
The minimum sleeper density shall be M + 7 in sections having traffic density above 10 GMT
and M + 4 in sections having traffic density below 10 GMT.
-
The ballast cushion shall be 20 cm.
Bridges shall be built to revised BG loading of 1975 with a maximum axle load of 22.5 tonnes
for the locomotive and a train load of 7.67 tonnes per metre behind the locomotives with maximum axle
load of 22.9 tonnes for train load.
(5) Group
`E'-Other sections of branch lines with present sanctioned speed.
-
The minimum rail section to be adopted will be 60 Kg in section having traffic density of over
20 GMT, 52 Kg in sections having traffic density from 10 to 20 GMT and 44.5 Kg in sections having
traffic density of less than 10 GMT.
-
The minimum sleeper density shall be M + 4. However, depending on local conditions a
density higher than M + 4 can be adopted where traffic density is 10 GMT and above subject to Railway
Board approval.
-
The ballast cushion shall be 15 cms.
Bridges will be built to revised BG loading of 1975 with a maximum axle load of 22.5 tonnes
for the locomotives and a train load of 7.67 tonnes per metre behind the locomotives with a maximum
axle load of 22.9 tonnes for the train load.
211. Meter
guage lines on Indian Railways is classified into various categories indicated below :
(1)
Trunk Routes.- Having a traffic density of 5 million G. T. Km per Km per annum and
above or where the speed will be above 70 Km hour (45 mph).
-
The rail section to be adopted shall be 37 Kgs (75 lbs.)
-
The sleeper density shall be M + 7.
-
The ballast cushion shall be 25 cms.
Bridges will be built to MGML standard of loading i. e. 13.2 tonnes axle loads and a train of
3.87 tonnes per metre run behind the engine.
(2)
Main lines (other than trunk
routes). - Having a traffic density of 2.5 to 5.0 million G. T.
Km per Km per annum.
-
The rail section to be adopted shall be 30 Kg.
-
The sleeper density shall be M + 7.
-
The ballast cushion shall be 20 cms.
Bridge will be built to MGML standard of loading i. e. 13.2 tonnes axle load and a train of
3.87 tonnes per metre run behind the engine.
(3)
Other main lines and branch
lines. Having a traffic density of 1.25 to 2.5 million G. T.
Km per Km per annum.
-
The rail section shall be 30 Kg.
-
The sleeper density shall be M + 4.
-
The ballast cushion shall be 20 cms.
Bridges will be built to MGML standard of loading i. e. 13.2 tonnes axle loads and a train of
3.87 tonnes per metre run behind the engine.
(4)
Tertiary
lines. Having a traffic density of below 1.25 million G. T. Km per Km per annum.
Bridges will be built to MGBL standard of loading i. e. 10.7 tonnes axle loads and a train of
3.87 tonnes per metre run behind the engine.
212. The use of second-hand rails is permissible, provided that they have not lost more
than ten per cent of their weight and, having regard to the volume of traffic expected, that their anticipated life
in the new line is not less than ten years.
213. Railway Administrations may decide, on the merits of each particular case, the
standard of ballasting necessary on first opening.
Surveys
214. Scope of Survey Operations.
(A)
As a general rule the work necessary under Preliminary or a final location survey
will be :
-
(1) Staking out of the centre line;
-
(2) Levelling alongwith the centre line, with transverse levels where necessary and cross
sections of important rivers;
-
(3) Plane Table Survey of a Strip of country 100 metres on each side of the centre line;
-
(4) Plane Table Survey of rivers requiring a provision of a water way of 110 sq mts. or
upwards;
-
(5) Plane Table Survey of Station
sites.
(B) Where suitable aerial photograph are available for carrying out Preliminary Engineering
Survey by Photogrammetric Technique, the following works will suffice :
-
(i) Provision of Centre line pillars at approaches of important bridge/portals of tunnels, and at
important road crossing and station sites.
-
(ii) Preparation of plan for minimum 100 mts on each side of the proposed centre line. The plan
shall also show inter-alia, identifiable points with their description to enable centre line being
picked up;
-
(iii) Longitudinal Section along the Centre Line.
-
(iv) Strip plans of rivers requiring a provision of water way of 110 sq. mts. or upwards with cross
sections.
-
(v) Strip Survey of Station sites obtained from Photogramatic plotted survey plans.
Alignment
215. In fixing the alignment of railway line, the following points (para 216 to 221) require attention.
216. Position of
Curves.-It is preferable to have cuttings and tunnels on straight track but
they may be provided on curves if the cost of having them on the straight is excessive.
217. Degree of
Curvature.-The sharpest degree of curve to be adopted should normally suit
the projected speed corresponding to the category of line proposed. Sharper curves with speed
restrictions may, however, be proposed where the cost of keeping down the curvature within the normal limit would
be excessive. In the case of survey for additional lines, the guide lines indicated in para 236 may be
referred to. In planning the layout of curves for new constructions and additional lines on category `A' routes
for Broad Gauge maximum cant of 185 mm may be assumed for the purpose of locating all
permanent structures etc. by the side of the curves on a line having a potential for increasing speeds in future.
218. Transition
Curves.- The shape of transition shall be a cubic parabola with a linear.
The length of transitions should correspond to the speed projected of the projected line and in the case
of category `A' of BG the length should be worked out on the basis of 185 mm cant. The cant gradient
shall be so chosen that the rate of change of cant/cant deficiency at the maximum permissible speed does
not exceed 55 mm/sec. under any circumstances for BG lines. For the purpose of designing the future
layout of the curves, a cant gradient of in 1.200 shall be aimed at for BG lines.
219. The desirable minimum length of
straight between reverse curve should be 50 m for BG.
220. Gradients
- Sags in cuttings should be avoided to the maximum possible extent. If
possible sharp changes of gradient should be avoided on curves.
221. Vertical Curves
- Vertical curves shall be laid out only on those points of change of
grade where the algebric difference between the grade is equal to or more than 4 MM/Metre. The
minimum radius of the vertical curves shall be 4000 M for `A' category, 3000 M for `B' category & 2500 M for `D'
and `E' categories lines in the case of Broad guage and 2500 M in case of all categories of Metre
Gauge routes.
222. Alternative Alignments
- Where alternative alignments of importance have been
examined and rejected their trace should be indicated by a dotted line on the plans and the reasons for rejecting
the alternative should be explained in the reports.
223. Plane Table
Survey - As a rule where Plane Table Surveys are carried out all details
within a distance of 100 metres of the final alignment should be observed. Particular care should be taken in
determining the boundaries of village land in entering on the plans any other details required for
the preparation of land plans. The State Government's requirements for the notification for land
Acquisition should be studied for the purpose. The position at which transverse levels and cross sections of
rivers have been taken should be clearly marked on the survey plans.
Rivers
224. Important
Rivers- If a correct survey of and important river does not exist, the river
should be surveyed for a distance of 8 kms. up stream and 2 kms. down stream, all spill channels up
stream being shown on the plan; these distance of 8 and 2 Kms. are to be taken as measured at right angles to
the centre line of the Railway and not along the course of the river.
225. Gross section should be taken of the river bed at suitable points and the position marked
on the survey plan. The level of the highest known flood or ordinary flood and of ordinary low water should
be noted on each cross section. The average slope of the river bed is to be determined from a point about
2 Kms above the railway crossing to a point 2 Kms below the same. In case there are sharp changes in
the bed slopes the local bed slope will have to be determined over a shorter length.
226. High Flood Levels -
Whenever reliable information of high flood levels can be
obtained they should be observed frequently and noted. This information is required when deciding on the
formation level.
227. Diversion of Rivers
- Should it be considered desirable to divert the course of any river
or stream, the best method of doing so should be examined, the necessary surveys and sections made,
and the diversion shown on the survey plan.
228. Protection Works
- Protection works required to prevent encroachment of rivers, to
mitigate the effect of bursting of tanks or scour of surface water in the vicinity of the line, should be
carefully considered on the ground and the position and extent of such work determined and surveyed, high
flood marks of spill water should be carefully sought out and recorded on plans and sections.
229. Construction of New Railway Bridges
- Whenever new Railway bridge are built on new lines involving either (i) spans of 24.384 m (80 ft) and above, or (ii) waterways of 304.8m. (1,000 ft.)
and above, or (iii) well foundations, a decision should be taken whether the sub-structures should be built :-
-
(a) In the case of metre gauge bridge to suit broad gauge loading, or
-
(b) In the case of broad gauge single line bridge to allow for future doubling.
In order to enable the Railway Board to decide what should be done, additional
information should be given in the Survey Reports as indicated below for each of the bridge falling under each of the
three categories given in sub-para above :-
-
(a) In the case of metre gauge bridge, the additional cost of building the Sub-structures to
broad gauge loading, and
-
(b) In the case of broad gauge single line bridge the additional cost of building sub-structures to
allow for future doubling.
230. Provision of traction over-head equipment structures on new bridges
- In all case of new construction, doubling, avoiding lines and fly-overs, irrespective of the fact whether the section islikely to be electrified in the near future or not, provision should be made in the piers for holes for
fixing OHE masts in future in the cases of bridges with a total opening of 45.72 metre (150 ft.)
Station Sites
231. (A) Station Sites
- The position of station Yards should be almost the first thing to be
looked for in a survey in level country. The common practice of joining up important villages by straight lines
on maps of 0.5 Kms. to 1 cm. scale often result in the introduction of unnessarily sharp curves near
stations. It generally pays to select a station site on the ground and to produce the straight line through the yard
as far as outer signals in both directions before turning in the direction of the next obligatory point. The site
for stations should be completely surveyed in such details as to be suitable for plotting to a scale of 10 m to
1 cm and cross sections should be taken, if necessary.
This detailed survey should take in every thing within the proposed boundary of the station yard.
The dimensions of the plot of ground intended for the station yard should be sufficient to allow ample
space, not only for first requirements but also for extended accommodation likely to be needed to meet
increased traffic in the future. Care should be taken to make arrangements for sufficient land outside the
boundary of the station yard, for borrow-pits or spoil banks. Borrow-pits near station yards are
undesirable,
because they provide breeding grounds for mosquitoes and endanger the health of the railway staff and of
other persons living in the vicinity.
(B) Where suitable aerial Photographs are available for carrying out preliminary survey
by photogrammetric technique, plans for station site may be prepared by enlarging the plans obtained
from aerial photographs.
232. If possible, a station should not be near a curve, but if this is unavoidable, the question of
the view of the outer signal should be considered. No steep falling gradient should, if it can be avoided,
begin within 45 metres of the outermost point. The possibility of new intermediate crossing stations
being introduced, when traffic develops, should be considered in grading the section and in fixing the position
of stations for first construction. The distance between sites selected for stations should, as far as
possible, having due regard to local conditions, be multiples of the ultimate distance apart of crossing stations
when traffic is fully developed.
233. Junction
Arrangements. --Except in the case where a new line is of a different guage
and has entirely its own arrangements, the plans and estimates for the junction should be prepared in
consultation with the open line administration of the existing railway. As a rule it is advisable to join nearly 2 Km
away from the centre of the junction and hence run parallel to the existing line.
234. Survey for the Provision of Additional
Lines. In carrying out the survey for the
provision of additional lines (alongside the existing track) the following points require attention (para 235 and 236.)
235. The projected line should be laid parallel to the existing line as far as possible on the
right hand side or on the left hand side, depending on
-
(i) Location of telephone and telegraph wires.
-
(ii) Location of existing station buildings and other goods facilities;
-
(iii) Construction of new bridges with least interference to traffic on the existing line as far as
possible;
-
(iv) In sections where there are pronounced directional movements of empty and loaded traffic,
the possibilities of running heavier train loads with multi-engine operations and its effect on
the existing bridge structures should be taken into account.
236.
While determining the alignment for the additional lines, the following points have
to be considered :
(i) Existing bridges should be extended wherever possible with tracks to the same track centres
over the bridge portion as on approaches thereby avoiding reverse curves.
(ii) Adequate vertical clearance for
bridges contained in “IRS Code of Practice for the Design of Sub-Structures
and Foundations of Bridges" should be followed, irrespective of whether
specified free-board is available or not under the existing bridges. On
sections where the raising of track to obtain the required routes and main
clearance is impracticable or is otherwise prohibitive in cost, Railway
Board's prior approval is required to be obtained for waiving the clearance
requirements.
(Authority: Railway Board letter No.2011/CE-I/BR/BSC/81/Seminar/Pt.2 dated
01.05.2014)--acs no.48
(iii) The degree of curvature to be adopted on the new line should suit the projected speed
corresponding to the category of line. At locations where the new alignment is being located
on the outside of existing curves which are sharper than the limiting degree of curvature
compatible with the projected speed of the line, the new line has to be located further away
to avoid infringements, which will involve additional cost unless the existing curves are also
realigned before the construction of new line.
237. Gauge Conversion Surveys.--In carrying out Gauge Conversion Surveys, the
objective should be to use the existing assets including formation, bridges, building signalling and permanent
way without strengthening if possible and with strengthening if necessary. The following points (Para 238
to 242) require attention.
238.
Alignment. --In deciding the alignment of the proposed gauge a decision will first have to
be taken whether the retention of the link of the existing gauge in addition to the new gauge is essential
on operational considerations. The link may be maintained either by having mixed gauge on that section
or independent parallel lines of the new gauges. In sections where the old gauge is not to be retained,
the following alternatives are available for consideration :
(i) Straight
Conversion.--In this case the centre line of the existing gauge and the proposed
gauge are the same. This procedure is to be normally followed within the constraints of
grade and the degree of curvature indicated in the terms of reference.
(ii) Shifted
Alignment.--In this case the centre line of the proposed gauge is shifted marginally
to take some advantage e. g., to use existing platforms or to avoid difficulty in executing
earth work like widening of long cutting so that widening is done on one side etc.
(iii) Parallel
Alignment.---n this case the alignment of the proposed gauge is taken away
from the existing alignment. Advantage in following this method is that all work can be
carried out without interfering with the existing track. If there is considerable difference in
the rail levels between existing and proposed tracks or if a large number of bridges
require reconstruction than the adoption of this method requires consideration.
(iv) Diversion--.In this case the proposed alignment is taken completely away from the existing
alignment for long lengths. This method is adopted in the case of ghat sections, when the
existing track is having very sharp curves and steep gradients.
239. Re-alignments of
Curves. The higher speed permitted on the proposed gauge will
require provision of long transition curves, which will cause a shift of the entire curve inside, which should be
kept in view. There may be sharp curves in the existing alignment and the question of retaining some of
these curve with speed restrictions or flattening them will have to be decided by working out the cost the
realignment vis-a-vis advantages to be gained.
240. Formation.--While it is desirable to provide standard width of formation of banks for
the proposed gauge in such of the stretches where the alignment passes through built up areas and
the acquisition is difficult and also expensive, adoption of lesser widths and sleeper slopes in good soil
condition areas has to be considered. In some cases provision of the walls may also have to be examined. In
the case of cuttings, it may be possible to retain the existing widths of cuttings by making side drains
pucca and covering them with RCC slabs. When this is not possible for any reason the cutting can be
widened to 5.49 m (18 ft.) in the case of BG exclusive of the side drains. In doing so widening of cutting all
through can be avoided by adopting a slightly sleeper slope than what is existing especially in the case of
stable cutting. Each case, however, has to be decided on its merits after taking into account the soil
characteristics and other relevant factors.
241. The possibility of retaining the existing sub-structures of bridges with overstress to
the permissible extent with or without strengthening should be examined. Where the condition of bridge
is otherwise satisfactory and adequate free board clearance is available, wholesale re-building of bridges
to the standard of the proposed gauge can be avoided, by suitable strengthening of sub-structures.
242. On girder bridges the adequacy of the piers to accommodate bed-blocks for the girder of
the proposed gauge and also ballast wall, in the case of abutments have to be examined, in addition to
extent of over-stress. When the condition of the arch is satisfactory and sufficient cushion is available or can
be provided, its retention may be examined by permitting 100% over stress in the arch masonry. Also
the strength of the arches can be determined by carrying out certain tests for which the RDSO may be
consulted. In the case of steel girders, their strength will have to be assessed and methods of
adequately strengthening them to the standards prescribed for the proposed gauge investigated, provided of
course, there is sufficient residual fatigue life left in the girders.
243. Railway Electrification Survey -
In carrying out the Surveys for Railway Electrification
the following points require the attention of Civil Engineer (paras 245 to 248). The terms of reference for
such Surveys shall be issued to the Civil Engineers by the Administration conducting such survey.
244. Similar to that mentioned in Paras 202 to 204 Railway Electrification surveys may also
be classified in two categories -
-
(a) Cost-cum-feasibility survey as a preinvestment
investigation to assist decision making and
-
(b) Foot-by-foot detailed survey as a post investment decision survey to assist preparation of
working designs and drawings for actual construction work.
In case of urgency it may be necessary to include portions of (b) alongwith (a), but normally the
two surveys are taken up separately.
245. Cost-cum-feasibility survey requires a quick survey of the route proposed for
electrification to examine the major civil Engineering installations which may have a bearing on the cost of
electrification. This will include study of heavy overline structure like fly-overs. Road over-bridges, through girder
bridges and long deck type girder bridge and tunnels to examine whether these will require major or
minor modification to permit erection of overhead equipment. An examination of the
proposed remodelling
plans, track renewals, reballasting including changes in the level of track, realignment of curves, all having
a bearing on track geomertry and the dates when these are proposed to be completed. This is necessary
as the OHE structure and traction OHE contact wire has to be kept at a fixed geomerical tolerance from
the track co-ordinates. In yards, a survey of tracks proposed to be wired will have to be examined for the
track centres to prepare slewing plans and assess their cost, for location of OHE structures. Feasibility
of running 12' wide EMU stock on suburban routes in vicinity of metropolitan cities will need to be
investigated. Availability of suitable land for location of locomotive shed, remote control centres. OHE S & T
maintenance depots will need to be examined. Also a quick survey of soil type over the route will reveal the cost
involved in foundations.
246. On acceptance of a project report, foot-by-foot detailed surveys are required for the
preparation of working drawing for the electrification Projects. This will need detailed examination of all the
items mentioned in para 245 above as well as that of light overline structures like carriage watering
arrangements, foot over Bridges, platform shelters, overhead carriage watering arrangements, and water columns,
to finalise the plans for their modifications, if required. Detailed, accurate survey of the route will
need examination of the above as well as pipe lines running alongside track, track centres soil types, all
needed to be examined for location of overhead equipment structures, sites for the various buildings required
for electrification are also required. To finalise the design of structures including those for overhead
equipment, it will be necessary to ascertain from the meteorological Department the wind pressures prevailing
over the route and determine the exposed locations subject to heavy winds, e. g., those on embankments,
in gullies with funnel effects and on bridges.
247. Based on the survey carried out as per para 246 above plans will need to be prepared.
For preparation of overhead equipment lay out plants, the survey plans in scale 1 : 1000 in open routes and
for yards 1 : 500 giving salient details, to facilitate preparation of pegging plans will need to be prepared.
This will need accurate marking of location of turn outs, crossovers, track centres, overline structures,
level crossings, bridges, drains and pipes running along the track as well as track centres.
248. Site plans marking locosheds/EMU car sheds, maintenance depots remote control
centres, control office, repeater stations and staff quarters are required to be made, Land acquisition plans,
if required will have to be finalised. All these will need to be finalised in consultation with open line.
249. Field Books.---All measurements and notes taken in the field should be neatly
recorded in field books, which should be the basis of all survey plans, drawings and reports prepared in
connection with a survey. The plotting of survey plans and drawings should, as far as possible, keep pace with
the field work.
250. Notes to be made in the field.-During the survey, careful notes with dates should
be made on the ground, from personal enquiry and observation, regarding any information likely to be
useful in working out the details of the projects, and in determining the prospects of the proposed line as a
commercial undertaking. The following points should receive special attention :
(i) Facilities for
Construction.-Materials for building, such as cement stone aggregate, sand
brick lime, fuel slate, timber, etc., and means for obtaining, working and preparing and
transporting the same. Arrangements for ballast and for sleeper supply. Style of roofing to
be adopted, Labour, skilled and unskilled, available in the district. Any special
difficulties regarding the supply of food or water, Prevailing rates and wages, and modifications in the
same likely to be caused by the construction of the railway. Means of transport by land
or water, existing or capable of development, and probable rates. Facilities for delivering
bridge materials, permanent way, etc. during construction. The use of temporary lines,
tramways & c. Depots for receiving and for warding material. Sites for temporary staff
quarters to be used during construction, taking into account the convenience of the situation
as regards the work, and also any conditions, such as water supply, likely to affect the
health or comfort of the occupants. Generally, any local conditions likely to affect rates or
methods of construction.
(ii) Formation.-The nature of soil for banks and cuttings and notes for use in grading the section;
trial pits should be sunk or borings taken where considered necessary to obtain this
information. Specimens of rocks and stone about which information is desirable, as to their
stability or suitability for building purposes, should be collected and submitted to the
Geological Survey Department for examination.
(iii) Bridgework.-Protection work and precautions to be taken against scour and encroachments
of rivers and streams, and particulars of diversions proposed. The waterway to be provided
for small rivers and streams and particulars of diversions proposed. The probable depth
and character of foundations for bridges and culverts, and any particulars to be taken into
consideration as affecting the design or construction of the same.
(iv) For rivers requiring a waterway of 110 sq. m. (1,200 square feet) or upwards, information
should, as far as practicable, be obtained regarding all circumstances likely to affect the
design of the bridge, the waterway to be provided, the depth and the character of the
foundations and other details. For example, the average rainfall over the area drained by
the river with particulars as to the amount and duration of any exceptionally heavy fall which
may have been recorded. The level of the highest flood determined from careful enquiries
on both banks of the river, the evidence adduced being examined and checked to such
extent as may be practicable. Any special floods, with particulars and dates. Any peculiarities
of the drainage area as regards form and declivity, and geological or botanical conditions
likely to affect the amount or velocity of the flood discharge. Physical characteristics of the
bridgesite or the river-bed in its vicinity as affecting the design of the bridge or the amount of
waterway required. Evidence of scour or liability of the river to alter its course. Nature and
extent of protection works likely to be encountered. Whether a roadway for cart, animal, or
foot traffic is likely to be required on the bridge, and whether there are existing roads in the
neighbourhood which could be joined up thereto. Particulars of road bridges and irrigation
works on the same stream in the vicinity of the proposed railway bridge be obtained.
(v) Stations.-The nature and extent of traffic to be expected at each station and the
accommodation to be provided on opening the line also arrangements for
extensions to
meet increase of traffic; the selection of suitable site with reference to nature of soil, depth
of foundation for buildings, water-supply and other conditions; the situation of the
station buildings on one side or other of the railway having in view the convenience of local
traffic, the positions of the neighbouring towns, roads, rivers & c., and the sites for crossing
stations which it may be necessary in the future to provide when traffic develops.
(vi) Road Crossing, Fencing,
etc. Means of crossing the line by level crossings and bridges,
under or over, width of roadway for crossing, and gradients to be allowed on approaches to
the same with reference to the class of traffic to be accommodated. Special facilities for
crossing to be allowed in the case of villagers owning a large amount of land on the opposite
side of the line from the village, diversions of roads. Provisions for canal irrigation channels,
and any special arrangements required for leading water from sources of supply on one
side of the railway to land laying on the other side. The extent and character of fencing to
be provided.
251.
The Operation of a Reconnaissance
Survey. Though not conducted in the same
detailed manner as or with all the instruments used in a Preliminary or Final Location Survey, will get
generally cover all the points covered by a Preliminary or Final Location Survey.
252. The scope of Traffic Survey is described in Chapter III.
General Instructions
253. Notification in Local
Gazette. Before any survey operations are commenced, a
notification in accordance with the terms of Section 4 of the Land Acquisition Act (See Appendix II) is to be inserted
in the Local Government Gazette. This should be arranged for by the Railway Administration as promptly
as possible after receipt of sanction to the survey, and is independent of the notification published in
the Gazette of India by the Railway Board.
254. Damage to Property and
Trespass.--The general sanction for a railway survey, given
by the Railway Board, does not authorize any interference with the rights or property of public bodies
or private individuals. The permission of the officer commanding should be obtained by the Engineer for
the entry of the survey party into any military cantonment, fort or entrenched post. In the case of
survey passing through a military cantonment, or civil station, the wishes of the officer-in-charge of the
cantonment, or civil station should receive due consideration, and his permission should be obtained before any
trees are cut or damage done to station property.
255. Compensation for
Damage. Where damage to private property is
unavoidable, compensation should, if practicable, be paid or tendered direct to the owner on the spot by the
engineer before the damage is done. In case of any dispute, the matter should be referred to the local
civil authorities to settle with the owner, and the compensation decided upon should be paid as soon
as practicable. Should the owner of the property be willing to clear the line himself, he should be allowed
to do so and be paid reasonable sum for labour in addition to compensation for the damage done.
256. Religious Edifices
etc. Every endeavour should be made to avoid interference with
religious edifices, burial grounds or other places or objects which may be considered sacred; where such place
or object is inclosed, the enclosure should not be entered except with the permission and in the presence
of the person in charge. Similarly, all possible steps should be taken to avoid interference with and
prevent the destruction of, ancient remains of archaeological interest.
257. Interference with Pre-existing Railways, Roads, Canals, etc.---Whenever the alignment of a new railway, passes close to or involves any alteration to, or diversion of, pre-existing railways,
roads, canals, etc., or interference with any work or land appertaining to the same, the written acceptance of
the authorities incharge of such railways, roads, canals, etc., to the proposals involved by the construction
of the new railway must in invariably be obtained before any work thereon is put in hand, and the
Railway Administration should, therefore, obtain the view of the responsible authority in such cases during
the survey.
258. Inquiry should also be made from the State Government in the irrigation Department by
the Railway Administration as to whether any dam or river diversion, or any work is proposed which
would affect the proposed, railway in any way. If after consultation with the Irrigation Department it is found that
any addition or alteration to the Railway would be required owning to such work as is contemplated by
the Irrigation Department being carried out, the Railway Board should be asked if provision for the addition
or alteration should be made in the estimates and plans.
259. Military Requirements.--
Where the line lies in the vicinity of a military post, camping
ground, rifle range or cantonment, the location should be decided by the Engineer in communication with the
local military authorities. Should it, however, be found that the military requirements would involve a
considerable extra expense in construction, or great inconvenience to traffic, or would be open to serious objection
from any engineering point of view, the matter should be referred to the Railway Board for orders.
260. In the case of important bridges the Railway Administration should consult the local
military authorities as to whether a roadway is required, and if so, what form of roadway is necessary,
particularly in regard to carrying heavy lorries and guns.
261. Assistance from Civil
Authorities. The local civil authorities should be freely
consulted by the Engineer during the progress of the survey operations, and their opinion should have due weight
in determining the most profitable route to be followed. They should be asked to use their influence, as far
as practicable, to protect the bench-marks, pegs and other railway marks from removal or injury.
262. The wishes of the local civil authorities should be obtained as to whether roadways
suitable for cart or foot-traffic are required on any bridge.
263. The wishes of the local civil authorities should also be ascertained as to headway and
width of span in the case of all bridges over navigable rivers.
264. The correct spelling of all towns and villages included in the survey should be taken from
the Alphabetical List of Stations, the Gazetteer or, if not found in either, from the civil authorities.
265. As soon as possible after the field work of a survey has been finished, the local civil
authorities should be supplied by the Railway Administration with an Index Plan, and requested to supply data
necessary for preparation of estimates of the cost of land for the projected railway (cf. para 901 et. seq.)
266. Local Governments or Administration should be supplied direct by the Railway
Administration with a copy of the project report and construction estimate, together with an index plan and section on
a scale of one cm. to 0.5 km. on which should be shown the size and positions of all waterways and
level crossings to be provided. The local Governments or Administration concerned should, at the same
time, be asked to express their views on the following points which, on receipt, should be forwarded to
the Railway Board;
-
(1) alignment,
-
(2) waterways, both in connection with existing channels and possible extension of irrigation,
-
(3) headways of bridges over navigable rivers, if any,
-
(4) roadways over important bridges (i. e., bridges with spans of 30.5 metres (100 feet) and
over and having a total length of waterway of not less than 110 lineal metres (1,200 lineal
feet) or 180 lineal metres (600 feet) in case the bridge is close to an important trunk road or
highway.)
-
(5) level crossings.
-
(6) sites of stations, and
-
(7) any other non-technical observations they may desire to make.
267. Quarterly Progress Report.---- Commencing from the quarter in which a Survey is
sanctioned, a report showing the progress of the survey during each quarter (ending 31st March, 30th June,
30th September and 31st December as the case may be) should be submitted regularly in form below (E. 267)
so as to reach the Railway Board before the 25th day of the month following the close of the quarter.
The submission of the progress report may be discontinued after the Survey Report is submitted to the
Railway Board.
Form E - 267
Progress Report of Surveys
..........................................................................
Railway.
Progress Report for the Quarter
ending .......................................................
(1) Name of
work ........................................................................
(2) Sanction No. &
date .............................................................
(3) Cost
.......................................................................................................
(4) Date of Sanction of
work ....................................................................
(5) Date of actual commencement of :
(i) Engineering
Survey
........................................................................................................
(ii) Traffic
Survey
................................................................................................................
(6) Actual percentage of Progress obtained by the
end of the month.............................
..........................................................................................................................................
(a) Field work.
(i) Engineering
Survey
............................................................................................
(ii) Traffic
Survey
.......................................................................................................
(b) Recess work.
(i) Engineering
Survey
............................................................................................
(ii) Traffic
Survey
......................................................................................................
(7) Target on which the Engineering and Traffic Survey reports should be submitted to the
Board's office.
...................................................................................................
(8) Special difficulties if any in progress of the surveys and in the compilation of the report...... .............................................................................................................................................
..............................................................................................................................................
|
268. Feasibility
Studies. Before commencing Project Investigation relating to
investments involving augmenting line capacity, improving terminal facilities or repair facilities, the Project
Investigator must ascertain from the user department the requirements of the user. Before proposals for new
marshalling yards, goods or passenger terminals and transship yards etc., are formulated, work study teams should
go into the actual working in the yard etc. (refer para 604-E). The Project Investigator must keep the
results of such studies in view while investigating the schemes. After developing the proposals the plans must
be got approved and signed by the concerned departments to avoid the substantial modifications at
a subsequent stage (refer para 604-E). Estimates must be based on such approved plans only.
****** |