    1 Signing of the Contract Agreement February 2006
    2 Commencement of Project April 2006
    3 Completion of Project October 2008 (original)
    4 Inception Report April 2006
    5 Current State Report May 2006
    6 Workshop No. 1 October 2006
    7 Mid Term Report December 2006
    8 Workshop No. 2 February 2007
    9 Draft Final Report (submission)  July 2010
    10 Draft Final Report (acceptance) January 2011
    11 Implementation at selected locations  July 2012