What's New Alert
   
High Level Committee’s recommendations on Disaster Management

Progress of Implementation of High Level Committee’s recommendations on Disaster Management as on 31.3.10

S.No.

Nodal

Directorate

Implemented

As on

31.3.10

Under Implementation

Total

 

Short Term

 

Medium Term

 

Long Term*

1

MECHANICAL

4#,5#,7,8,25,27,36,37,38,39,40,

42,52#,56,57,58,

59,60,61, 62,63,

64,65,66, 67,68,

70,71,72,73,74,

76,77,78#,79,81,

82, 83,84,85,86,

87,88,89, 90,92,

93,94,95, 106,

107,110,111

 (53)

 

 

 

2,9^,13, 69,75,

91,100,

102,104, (09)

62

2.

HEALTH

3^,11,18,19,21,

31,32, 41,53,

55,80 (11)

--

--

54 (01)

12

3.

SAFETY

1,12,14,15,109 (05)

 

-

33 (01)

16 (01)

07

4.

SECURITY

22,23,46,47,48,

49 (06)

--

--

--

06

5.

TELECOM

43,44,96,97

(04)

99 (01)

98 (01)

--

06

6.

COMMERCIAL

20,30,34,45,

50 (05)

--

--

--

05

7.

T&MPP.

101,103,105, 108

(04)

--

--

--

04

8.

CIVIL. ENGG.

24,29

(02)

--

--

--

02

9.

SECRETARY

6 (01)

--

--

--

01

10.

TRAFFIC

--

--

10^  (01)

1 7^(01)

02

11.

L M

26  (01)

--

 

--

01

12.

 ELECTRICAL

--

--

28  (01)

--

01

13.

FINANCE

      35 (01)

--

--

--

01

14.

CLAIMS

51 (01)

--

--

--

01

 

TOTAL

94

01

04

12

111

* - Action plan & time frame for implementation is to be decided by the directorates.
^Have been modified (3,9,10 &17)
#  Deleted by appropriate authority( 4,5,52,78)