CHAPTER XIX
ENGINEERING PLANT RESERVE
Custody, Receipt and Issue
1901. Object of a Reserve.-—In order to avoid losses from forced sales of serviceable and
useful plant left over from special works which is likely to be required for future special works, an
"Engineering Plant Reserve" may be created on each railway, with the previous sanction of the
Railway Board, who will fix the maximum financial limit of such reserve.
1902. Nature of Plant in Reserve Stock.—The Engineering Reserve would include items
of construction plant of the following description.—
1. Air Compressors
2. Air receivers
3. Boilers
4. Boring Plant, special, hand and power driven
5. Concrete mixing machine
6. Cranes (derrick scotch)
7. Dregers, crab
8. Drilling machine, hand or power drives
9. Drilling machines, pneumatic
10. Driving Gear
11. Engines, portable, steam
12. Engines, internal combustion
13. Engines, locomotive, 2 feet gauge
14. Gantries for girder erection
15. Hammers (pneumatic), rock drilling
16. Jacks, hydraulic
17. Jacks, screw
18. Jolly boats
19. Lathes (for construction)
20. Lorries (motor)
21. Mortar mills, steam power
22. Pumps and pumping plant of all description
23. Pile driving frames
24. Pile hammers, steam
25. Screwing machines
26. Steam hoists
27. Stone crushers
28. Winches, Crab
29. Winches, Steam
The list may be added to or any item deleted there from under the orders of the Chief
Engineer.
1903. The Stores Department should 'not hold separate stock of these items of the
Engineering Plan Reserve for use in building new work (not in the ordinary operations of the railway).
1904. Transfer of Plant to Reserve.—On the completion of special works and constructions,
all useful plant, for which there is no demand on the open line, should be returned by the Divisional or the executing Engineer-in-charge to the nearest stores depot accompanied by an
Advice Note (S. 1539) which should give the following additional information :—
1. Type of plant and maker's name in addition to full description.
2. Date when the plant was received.
3. Cost of plant originally debited to work.
4. Allocation of work on which the plant was employed and that to which credit for its
return value is to be afforded.
1905. The Advice Notes should be prominently marked "Engineering Plant Reserve".
Note —Where under existing arrangements the Engineering Plant Reserve is concentrated
in the Plant Depot under the control of the Engineering Department, the existing
arrangements may continue provided the rules in this chapter are followed mutatis
mutandis. If the plant released from a work is in good condition and fit for further
use without any overhaul or repairs, it may, with the permission of the Chief
Engineer, be transferred direct from one work to another on which it may be
required instead of being returned to the Reserve. The transfer value will be
fixed by the Chief Engineer on the basis of the formula laid down in paragraph
1913 for ascertaining second-hand value of assets.
1906. The Engineering Department will, in all cases, be responsible for deciding what
material is to be maintained in the "Engineering Plant Reserve".
1907. Custody of Reserve :—The Stores Department will be responsible for all material
in the Engineering Plant Reserve and should maintain records of their receipts, issues and
balances.
1908. Storage.—When any New material is sent to the Reserve or where an item is returned
from works to the Reserve, the Controller of Stores should decide at which point it is
tobe stocked
It is desirable that the plant should be stocked at some place close to where it can be over
hauled. It is not necessary that all the material should be held in one place, provided that
separate records are kept for all such items and the materials themselves are clearly marked and
stocked separate so that they do not get mixed up with ordinary stocks.
1909. For convenience, the material may be held in three localities :—
(i) Plant such as winches, dredgers and pumps, which required overhaul
in the workshop
may be kept in or close to the shop concerned.
(ii) Plant like portable engines, which have boilers, should be kept in or close to loco
shops, where the boilers can be inspected and tested.
(iii) Plant like disintegrators, pulsometers, tip wagons which may require replacement of
spare parts but not much shop work, may be kept in the stores depots.
1910. Reserve Plant Number.—Each machine or piece of plant should be given a separate
number and marked in some conspicuous place with this number and the letters "E.R." (Engineering Reserve). This number corresponds to the price list number assigned to general stores
items and is conveniently referred to as the Reserve Plant number. If there is more than one
machine or piece of plant of the same category, a bye number should be given to each such
machine as a denominator with the number allotted to the category of plant as numerator. If the
machine or plant has beengiven by the makers an individual number, such a number should be
adopted as bye number.
1911. Reserve Plant Register.—The Depot Officer should maintain a register form (S. 1911)
for recording the receipts, issues and balances of all "Engineering Reserve" items. This register
will show the following particulars :—
(a) Reserve Plant Number (vide paragraph 1910).
(b) Returning Officer.
(c) Name of work.
(d) Particulars of Advice Note under which returned.
(e) Description of plant.
(f) Cost of plant originally debited to works.
(g) Estimated scrap value of paint at end of life,
(h) Book value on receipt into Reserve.
(i) Total book value
(j) Particulars to issue notes under which issued from Reserve.
(k) Name of work to which issued.
(l) Amount debited on issue.
No other numerical ledgers need be maintained.
1912. On receipt of an item of Engineering Plant Reserve, the particulars of the plant should
be entered in the register from the Advice Notes form (S. 1539).
1913. Valuation of Plant.—The value of the plant sent to the Reserve will be fixed by
the Controller of Stores in consultation with the Chief Engineer, after a consideration of the original
value of the plant, the time which it has been in use and its condition at the time of return, as also
the current purchased price of new plant. In all cases 'special plant' purchased for work of a
kind that is not frequently undertaken, it should be seen that the value at which such plant is
taken into the Engineering Plant Reserve is as low as possible consistent with the possible price
the plant may fetch in the market. .The following formula maybe used as a guide in all other
cases. The value fixed should be entered in all the copies of the Advice Note (S. 1539) and the
several foils disposed of as usual.
Formula :—
The second hand value of a Plant is equal to :—
N
R-----------(R-S)
L
where
R is the present day price of a new plant; if this is not readily available, R may be estimated
taking the original price as a basis.
N is the age of the plant.
L is the average total life of the plant,
and
S is the scrap value (previously estimated).
1914. Inspection and Repairs of Reserve Plant.—On return of a plant to the stores depot
it should be inspected, dismantled and all necessary repairs carried out so that it is in through
working order and ready for the next issue.
1915. Responsibility for Inspection.—The Chief Engineer will be responsible for arranging
inspections of all materials taken into the Reserve and for certifying that all such material is
complete in all respects, serviceable and fit for immediate issue to another work.
1916. Requisition for Inspection.—On receipt of the material, the Depot Officer should
issue a memo, requesting the Chief Engineer to arrange for its inspection and to fix its monthly
higher rates in accordance with the rules laid down in paragraphs 1923 to 1939. If work, such as
More inspection, is required, the Depot Officer should also requisition the services of the
Mechanical Department for the work.
1917. Estimate of Cost of Inspection and Repairs.—Estimates of the cost of inspection
and of any necessary repairs should be obtained and sent to the Chief Engineer for acceptance
before any such work is put in hand.
1918. Allocation of Cost of Inspection and Repairs.—The cost of inspection and of repairs
required before bringing an item of the Plant Reserve to a fully serviceable condition on return
from a work should be changed to the work concerned, which should bear in addition the
difference between the second-hand value of the article as it stood when the item was supplied and
as it stands at the time of the return of the item determined on the lines indicated in paragraph
1913. In those cases where it is doubtful work there the plant will be used in the near future, and it is
therefore;, considered desirable not to undertake the repair immediately, the cost of such repairs
should be estimated and the value fixed for the plant after deducting such estimated cost of
repairs, A note to this effect should be given on the Advice Note (S. 1539) for plant, and transcribed
into the Plant Reserve Register (S. 1911) and Priced Ledgers for Reserve Plant (S. 1940). Where,
however, the arrangement is or the work to be debited on the basis of hire for the plant to be
inclusive of all charges, the expenditure on inspection and repairs and the deterioration in
value should be charged to the head A-2210. No suspense head or account should be operated
upon for the purpose of recording the expenditure op repairs to such plants.
1919. Certificate of Inspection.—The Depot Officer should obtain a certificate in the
following form for all material brought on or returned to the Reserve :—
Form No. S. 1919
ENGINEERING RESERVE PLANT INSPECTION CERTIFICATE
Reserve Plant No..................
Description of item................
Spares included....................
Remarks..........................
(,!) The material specified above is complete and ready for use.
(ii) The above material has been overhauled and inspected
on............................................the plant
is in good order and ready for re-issue to works.
The plant has been inspected and the following items of repair arc needed. The estimated
cost of such repairs is Rs.........................
...................................................
Chief Engineer
Dated....................
1920. On the certificate being furnished, the Depot Officer place the item in the Reserve
and see that debits for hire charges and cost of inspection and repairs are against the work from
which the material was received.
1921. Issue.—Issues will be made under instructions from the Chief Engineer who will
countersign any requisitions placed on the Depot Officer by the officials in charge of works.
Issue notes covering issues of plant from the reserve should be marked "Engineering Plant
Reserve" in bold letters. The Reserve Plant Number of the plant issued should invariably be quoted
on the issue notes which should also show the amount to be debited. This should be the same as
the value at which the item was taken into the Reserve. The several foils of the issue note should
be distributed as usual.
1922.. Freight and Handling Charges.—Freight and Handling Charges incurred in returning
the plant from 'works' to the stores depot, or vice versa will be borne by the party returning the
plant or indenting for it, as the case may be.
Hiring cut of Reserve Plant
1923. As many of the items of plant taken into the Engineering Plant Reserve are likely
to be idle for considerable periods, such of those as are not likely to be required for current
railway works may be hired out to other Government Departments, or private parties, with the
approval of the Chief Engineer, if the plant is to be used in the interests of public service and is
to be handled by Departmental labour only and not by contractors, and with the approval of the
General Manager in all other cases. Applications for "hiring the plant should be in the form
shown below.
Form No. S. 1923
APPLICATION BY OTHER GOVERNMENT DEPARTMENTS
FOR ENGINEERING RESERVE PLANT ON HIRE
To be filled in by prospective loanee
To be filled in by the Railway.
By Whom Requireded |
Particulars of plant required |
Quantity required |
Purpose for which required |
period for which required |
Original Cost |
Depreciated Cost |
How long used by Rly. |
Hire charges |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
. |
.. |
. |
. |
. |
. |
. |
. |
. |
Certified that the above plant will be used by departmental labour only and not by
contractors.
..................................
Signature of Loanee,
1924. Agreement Form for Hire of Plant.—A suitable agreement should be signed by the
Department hiring the plant and the Chief Engineer, incorporating the points dealt with by the
rules in paragraphs 1925 to 1939 of this Chapter. A copy of this agreement should be supplied
to the Accounts Officer, Stores, who will watch the recovery of higher, and the return of the
plant through the Register of Agreement (S. 503) into which the agreement will be posted by him
1925. Terms of Delivery.—Delivery shall be in the railway stores yard and the hirer shall
remove and return the plant from and to the same point at his own cost.
1926. Freight and incidental charges.—Where the plant material is carried by rail, the
carriage charges shall be at public tariff rates.
1927. The hiring department shall pay, in addition to the hire charges agreed to actual costs
plus 12| per cent supervision charges of all packing, handling, loading, unloading or other
direct charges incurred by the railway in despatching or receiving back the plant.
1928. Hire charges.—Hire shall be charged from the date of delivery of the plant in the
railway stores yard to the date of its return to the same point (both dates to be included in the
period of hire).
1929. Hire charges for each item of plant will be fixed by the Controller of Stores in
consultation with the Chief Engineer.
1930. Liability for Wear and Tear.—The hiring department should satisfy itself when
taking over the plant that it is in satisfactory working order. It shall be liable to replace at its
own cost wearing parts, such as washers, packing, pump buckts, gauge-glasses & c. which may
require replacement during the period of hire. A schedule giving a list of such parts to the
particuar plant hired out should be attached to the Agreement of Hire of the plant. Spares for such
replacements should be obtained only from the railway, which will supply them ex-stores depot,
at book rates plus the ordinary supervision and freight charges. The materials will be sent from
the stores depot to the railway station nearest the point where the plant is stationed, at Public
tariff rates, to be paid by the hiring department. The Chief Engineer may at his discretion permit
the purchase of the spare wearable parts from outside sources provided he is satisfiedth at parts
correct to specifications only will be used.
1931. Breakage or Loss of Parts.—In the case of [breakage or loss of any part or accessory,
other than the parts liable to wear out referred to in to schedule attached to the Agreement for
Hire of a plant, the cost of replacement shall be shared between the railway and the hiring
departments, the railway accepting a fraction of the cost represented by the actual life of the part
N
divided by the assumed life, i.e. L—N x —(vide paragraph 1913) and the hirer a fraction of the cost
L
represented by the difference between actual and assumed life divided by the assumed life i.e-
R
L—N x--------(vide paragraph 1913). Unless expressly stated before hand in
writing, all part,
L
and accessories shall be taken as having the same life as shown for the plant on the railway
books; the assumed life of all machines when not otherwise stated shall be taken as 15
years.
1932. Loss of the Entire Plant.—In the event of the loss of the entire plant, the cost shall
be divided on the basis laid down in paragraph 1931.
1933. Statutory Certificates, & c, While the machine is in the possession of the hirer
he shall be responsible for seeing that any inspection certificate or licence required under any
Government Act is obtained in due time. The hirer is also responsible for seeing that all required
precautions areobserved in using the plant, and is responsible for any accident which may occur
from the use of the plant.
1934. Access to Plant at Hirer's Premises.—The railway shall be given reasonable
acces
to that plant and such facilities as may be necessary to satisfy itself that the plant is being so used
as to avoid any unnecessary wear or loss or undue risk.
1935. Right of Recall.—The railway shall reserve to itself the right to recall any plan
without assigning any reasons by giving one month's notice, or at any time without notice in the
event of its being required by the railway for an unforseen emergency. The general nature of such
emergencies should be specified in the Agreement for the hire of the plant. In either case, the
railways shall not be liable to pay any compensation to the hirer for the loss that may be caused
by the withdrawal of the plant.
1936. Inspection and Repairs on Return of Plant.—On return of the plant, it should be
opened out and examined in the railway shops. A statement should be prepared of any repairs or
replacements, other than those due to fair wear and tear, which are considered necessary, and the
cost of such repairs or replacements should be estimated and shown thereon. A copy of this
statement should be sent to the hirer who should be given reasonable opportunity, during working
hours of the stores depot, to check the correctness of this statement by the examination of the
plant. Such repairs and replacements as are agreed to be necessary, over the above fair wear and
tears shall be shared between the parties on the same basis as for breakage or loss of parts, vide
paragraph 1931.
1937. If the Chief Engineer or other officer empowered by him in this
behalf is
that the breakage referred to in paragrah 1931 or excessive wear and tear referred to in paragraphs
1936 is not due to the conditions of service to which the plant has been subjected to by the hirer,
but is due to previous wear, inherent defect not incidental to the service on
which the plant has been
used or the like, the Chief Engineer or other officer empowered by him may waive wholly or in
part the recovery of cost.
1938. Accountal of Hire Charges.—The Controller of Stores will be responsible for the
due recovery of the hire charges and the charges for inspection and repairs, where lived, and
for the correct maintenance of the numerical accounts of the several items included in the Engineering Plant Reserve.
1939. (a) The account of the hire charges of the plant should be kept by the Controller
of Stores and this should be inspected by the Accounts Department at the time of inspection of
his office. The amount of hire should be credited to Earnings.
(b) The bills for hire charges should be prepared by the Controller of Stores and submitted
through the Stores Accounts Officer to the hiring departments. The Stores Accounts Office
will arrange for the check and recovery of the hire charges.
PROCEDURE IN THE ACCOUNTS OFFICE
1940. Priced Ledgers.—Separate Priced Ledgers should be maintained in the Stores Account
Office for each plant or piece of plant represented by a Reserve Plant number. The priced ledger
should be maintained in the following form.
Form No. S. 1940
ENGINEERING PLANT RESERVE PRICED LEDGER
Description
of Plant..............................................................................................Serial
No.......................................................
Bye No. of Plant |
Original
New cost (estimated when not known |
Estimated
scrap value when unserviceable |
Original
debit to work |
Advice Note or issue note |
Received
from or issued to |
Name of
work |
Opening Balance Rs. |
Credit allowed Rs. |
Debit
raised |
Closing balance Rs. |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
. |
. |
. |
. |
. |
. |
. |
. |
. |
. |
. |
1941. The priced ledger should be posted in the same manner as other vouchers. The entire
"Engineering Plant Reserve" being treated as one class for the purpose of Class Summaries and
Class Ledgers. The receipt and issue vouchers affecting this Reserve should be dealt with
on the same lines as the other vouchers for stores transactions. The balance at the end of each
month in the Class Ledger should agree with the debit outstanding under the head "Engineering
Plant Reserve" in the General Books of the railway and should not exceed the financial limit
laid down by the Railway Board as mentioned in paragraph 1901.
|