CHAPTER XIV 

ESTIMATES AND COMPLETION REPORTS

A. Estimates



1401. Estimates.—Detailed estimates for works to be undertaken in railway workshops should be prepared in the following cases:—

(1) All  works whether chargeable wholly or in part to Capital or to Depreciation Reserve Fund or to Open Line Works—Revenue (including New Minor Works) and works of a special nature, such as special overhauls of rolling-stock even though chargeable to ordinary revenue.

(2) Works undertaken for outsiders (including those for Home Line Employees), other Railways and other Government Departments or Ministries.

No detailed estimates need, however, be prepared in the case of new minor works costing Rs. 5000 and less each for repair and reconditioning works each costing not more than the following limits:—

Locomotives

Rs. 25,000 

Carriages (including rail cars)

Rs. 12,500

Wagons, tenders, boilers and service motor cars

Rs. 5,000

Note: The provisions of this para will not apply to the manufacture of Locomotive/Coaches or furnishing work undertaken in Railway Production Units against orders placed by the Board for supply to Railways.

1402. Form of Estimates.—The estimates should be prepared in quadruplicate in Form No. 1402. One copy should be retained as office copy, the other three copies being sent to the Workshop Accounts Officer. The Workshop Accounts Officer will retain one copy and return two copies duly checked and certified to the authority competent to sanction the work through the Deputy Chief Mechanical Engineer (or the Works Manager). The authority sanctioning the work should retain one copy and return the other duly sanctioned to the Deputy Chief Mechanical Engineer or the Works Manager as the case may be.

Form W. 1402

OUTER SHEET (FRONTPAGE)

..........................Railway

ABSTRACT OF COST OF WORK



................................Department                                                     Office  .........................................

Estimate No...                                                                                                       19 .................................................................

Framed by ............................................     Designation ...........................  

Region............................................           Division .........................            Station ... ..................................................

Name of work ............................................Reference ...............................................

Place No................................................................

Estimated Cost

Sub-heads of work Cash Total Original total in case of revised estimate
Work Stores Stores
. . . .

Allocation

Capital DF DFR OLWR Ordinary revenue Deposit Misc. Advance Total

Funds............................to be provided from budget for.......................................item No...................................direct or by reappropriation.

Report and justification

Specification..............................                                                                                      Signature...................................

Drawings and Armexures                                                                                                 Designation.................................

No............. Date..................                                                                                Sanction registered as

Incidence andallocation verified

(subject to checknote attached).

This requires sanction of the....................                                                                          No............... Dated......................

FA & CAO                                                                                                                     GM/CME/Dy. CME/WM.

Form No W. 1042

ALLOCATION STATEMENT 

Allocation Statement

Main and Sub-heads Cash Rs. Stores Rs. Total Rs. Capital
. . . . .

 

DRF DF OLWR Ordinary Revenue Deposit
. . . . .

Form W. 1402

........................Railway

MECHANICAL DEPARTMENT __STATEMENT SHOWING DETAILS OF ESTIMATED COST

Name of work. ..............................................

Department ..................................................   Division................................................ Station......................................

S. No. Description Quantity  Rate Unit Cost
Cash Stores Total
Purchase Stock .
1 2 3 4 5 6 7 8 9

Allocation

Capital DF DRF OLWR Ordinary Revenue Deposit Misc. advance Total Remarks
10 11 12 13 14 15 16 17 18

Office, Station...............................                      Signature... ..................................

Date ..........................................                         Designation .................................

1403. Estimates for Rolling-stock Addition.—In the case of rolling-stock to be built and provide inter alia for the following items being shown separately:—

(i) Locomotives, Boilers and Wagons:—

(i) Cost of engines, boilers or wagons including sea freight, etc. in rupees at the prescribed rate of exchange, if obtained from abroad, if obtained in India, the likely contract price.

(ii) Customs duty (if obtained from abroad).

(iii) Freight and /or haulage charges when chargeable direct to work as forming part of cost of stores.

(iv) Sundry stores for erection.

(v) Labour for erection, 

(vi) Shop Oncast (for erection). 

(vii) General Oncost (for erection).

(viii) Percentage charges for height on stores (such stores the cost of which is not inclusive of such charges).

(ix) Pro Forma Oncost, to the extent chargeable (paragraph 1427).

(x) Contingencies
(xi) Write-back of the original cost of replaced stock  } In the case of replacement, renewal  and abandonment works
(xii) Credits for released  only, material 

(2) Coaching Stock:—

(i) Cost of underframes with wheels and axles. etc. including sea freight in rupees at the prescribed rate of exchange, if obtained in India.

(ii) Customs duty (if obtained from abroad).

(iii) Freight and/or haulage charges when chargeable direct to work as forming part of cost of stores.

(iv) Body fittings and stores including paint obtained for construction, inclusive of customs charges, if any.

(v) Electrical equipment, 

(vi) Timber, 

(vii) Sundry Stores, 

(viii) Labour, 

(ix) Shop Oncost, 

(x) General Oncost.

(xi) Percentage charges for freight on stores (such stores the cost of which is not inclusive of such charges).

(xii) Pro Forma Oncost, to the extent chargeable (Paragraph 1427).

(xiii) Contingencies.

(xiv) Write-back of original cost  }   In the case of replacement, renewal and abandonment works only
(xv) Credits for released material 

1404. Estimates for Workshop Machinery.—Estimates for the provision of workshop machinery should show—

(i) The cost of each machine, including sea freight in rupees at the prescribed rate of exchange, if obtained from abroad; or the contract price, if obtained in India.

(ii) Customs duty (if obtained from abroad).

(iii) Freight charges when chargeable direct to work as forming part of cost of stores.

(iv) Foundation charges.

(v) Wiring charges.

(vi) Erection charges, 

(vii) Shop Oncost, 

(viii) General Oncost.

(ix) Percentage charges for freight on stores (such stores the cost of which is not inclusive of such charges).

(x) Pro forma Oncost, to the extent chargeable (paragraph 1427).

(xi) Contingencies.

(xii) Write-back of original cost  }   In the case of replacement, renewal and abandonment works only
(xiii) Credits for released material 

1405. Schedules of Carriage Material.—Estimates for the construction of coaching stock should be accompanied by schedules showing full particulars of the quantities and cost of the materials required preferably in the following detail:—

(1) Bogie-

(i) Bogie

(ii) Wheels and axles.

(2) Underframes and attachments—

(i) Underframe proper, 

(ii) Buffing and draw gear 

(iii) Miscellaneous

(3) Underframe fittings—

(i) Vacuum Air/brake details.

(ii) Water tank connected fittings and pipe work.

(iii) Miscellaneous 

(iv) Hand brake arrangements.

(4) Carriage body—

(i) Bottom framing

(ii) End framing 

(iii) Side framing 

(iv) Doors and windows

(v) Partitions 

(vi) Roof 

(vii) Seats 

(viii) Bunks and racks

(ix) Footboards and sundries.

(5) Carriage Fitting—

(i) Fittings for bottom framings.

(ii) Fittings for end framings,

(iii) Fittings for side framings, 

(iv) Fittings for doors and windows,

(v) Fittings for partitions. 

(vi) Fittings for roofing, 

(vii) Fittings for seats. 

(viii) Fittings for bunks and racks, 

(ix) Fittings for floorboards and sundries.

(6) Electrical Fittings-—

(i) Dynamo with suspension gear. 

(ii) Accumulator box with fittings, 

(iii) Switch panel with hangers. 

(iv) Body fittings,

(v) V.I.R. Cable

(vi) Body woodwork, 

(vii) Miscellaneous stores, 

(viii) Compressors.

(7) Paint.

1406. The provision for timber, body fittings and for sundry stores should be based on actual for similar or other vehicles previously built, suitable allowance being made for fluctuations in prices and other known changes. Estimates for electrical equipment should be obtained from the Chief Electrical Engineer.

1407. Report accompanying the Estimate.—The necessity or the financial justification for the work should be briefly explained either in the estimate itself or in a Report accompanying the Estimate and a certificate appended that funds exist. The certificate of funds should be given with reference to the provision under Capital, Depreciation Reserve Fund, Development Fund, Open Line Works Revenue and Ordinary Revenue in the Works, Machinery and Rolling Stock Programme, as supported by the approved programme of works or of rolling stock or of Plant and Machinery. In those cases in which the provision made in the budget under Capital Depreciation Reserve Fund. Development Fund, Open Line Works—Revenue or Ordinary Revenue is less than the amount of the estimate (Capital, Depreciation Reserve Fund, Development Fund, Open Line Works—Revenue or Ordinary Revenue portions) or if there is no provision in the budget, it should be shown how it is proposed to find the amount required for expenditure, i.e. whether this would be met from savings in the provision for other items in the budget. The particular items under which savings are expected should be indicated along with the reasons therefore.

1408. Estimates for Renewals and Replacements.-— In case of replacements of rolling-stock, a note should accompany the Estimate giving full particulars of the stock to be replaced, such as—

(i) The distinguishing codes and numbers;

(ii) The dates of purchase or the approximate ages;

(iii) The original cost, reference being given when possible, to the relevant Completion Report; if the original cost is not ascertainable, it should be estimated;

(iv) The amount of original cost charged to Capital, if the total is not so charged; and

(v) The materials likely to be released from the stock replaced.

The note should also show the tractive effort, the seating capacity, the floor area or the carrying capacity or other appropriate information of each of the replaced and of the replacing units of stock as may be necessary to determine the amount of improvement, if any, involved in the replacement. The cost of fittings in the replaced and replacing rolling-stock should be shown where such cost is taken into account separately for purposes of allocation.

1409. Before submitting estimates for renewals or replacements, it should be critically examined whether it would not be possible to avoid or, at least, postpone such replacements by adopting methods of "reconditioning" at a cost that could be justified financially. In all cases in which reconditioning is decided upon, the total cost of reconditioning an asset should be charged to "ordinary repairs and maintenance" in the same way as the cost of other repair work. Detailed estimates should, as already stated in paragraph 1401, be prepared for all such works the cost of which exceeds Rs. 20,000, the limits prescribed therein.

1410. In all cases in which it is considered necessary to replace an asset, instead of reconditioning it, it should be examined (vide paragraph 1411) whether the average annual cost of service of the new asset is likely to be less than that of the old asset after reconditioning.

1411. "Average Annual Cost of Service" of an Asset.—The average annual cost of service of an asset is the sum of

(1) the average annual expenditure that would be incurred in connection with the upkeep operation, maintenance and repairs of the asset;

(2) the annual sinking fund payment to the depreciation fund; and

(3) the annual interest charges on the cost of the asset.

1412. The following example is intended to illustrate the method of financial justification to be employed when, with the data given below, it has to be decided whether a locomotive should be replaced or reconditioned:—

Particulars Old Locomotive  New Locomotive
Cost of the Locomotive . Rs. 50,000  (second hand cost) Rs. 5,00,000 (New cost)
Cost of reconditioning Rs. 50,000 .
 Rate of interest . 6 per cent 6 per cent
Life 10 years  40 years
Scrap Value Rs. 10,000  Rs. 20,000
Maintenance, Operation and Repair Charges Rs. 50,000 a year  Rs. 40,000 a year



The average annual cost of the existing locomotive after reconditioning would be Rs. 62,831 made up of the following:—


(a) Cost of maintenance, operation, repairs etc.

Rs. 50,000
(b) Interest at 6 per cent on Rs. 1,00,000 (Rs. 50,000 plus Rs. 50,000)  Rs.   6,000
(c) Sinking Fund payment at 6 per cent (90,000 x 0.0759) Rs.   6,831

 Total              

Rs. 62,831

The average annual cost of the new locomotive would be Rs. 75,250 made up of the following: —

(a) Cost of maintenance, operation, repairs etc.

 Rs. 40,000
(b) Interest at 6 percent on Rs.5,40,000 (i.e., new cost Rs.5,00,000 + the second hand cost of the old locomotive, Rs.50,000 minus the scrap value of the old locomotive Rs.10,000)    Rs. 32,400
(c) Sinking Fund payment at 6 per cent  (4,80,000 x 0.0065)  Rs.   3,120

 Total              

Rs. 75,520


1413. It follows from the above figures that, with the data assumed, it is cheapen to recondition the old locomotive instead of replacing it by a new one.

1414. Estimates for New Minor Works.—Detailed estimates for works chargeable to "new minor works", each costing over Rs, 5,000 should be prepared on the same form as it used for capital works.

1415. Revised Estimates.—As soon as it becomes apparent that the expenditure on a work or project is likely to exceed the amount provided there for in the detailed estimate, a revised estimate should be prepared and submitted for the sanction of the competent authority. It should, unless otherwise ordered by the sanctioning authority, be prepared in the same form and the same degree of detail as the original estimate, showing the excess or saving under each sub-head of estimate against the latest sanction. in cases where a supplementary estimate or a previous revised estimate has been sanctioned by the Railway Board, it should be made clear how the original sanction has been modified by such further sanction. In cases, however, where the work is in art advanced stage and is likely to be completed before a revised estimate is got out, the excess may, with the prior approval of the competent authority, be dealt with in the Completion Report (W. 1469) of the work. The fact that a competent authority has permitted the regularization of excess over an estimate through the completion Report should invariably be intimated to the Account Officer.

1416. Revised estimates should also be submitted where there are Material Modifications (see paragraphs 1108 to 1113) of the Indian Railway Code for the Engineering Department) in the sanctioned estimate.

1417. Estimates of work for Public /Private Bodies and Home Line employees.:-No work should be undertaken in Production Units, Railway Workshops for home line employees for the manufacture or repair of articles or supply of material. In the case of Public/Private bodies, such work may be undertaken in Production Unit/Workshops if the Chief Mechanical Engineer of Production Unit/Chief Workshop Manager (SAG) of Railway Workshop is satisfied that surplus capacity exists in the Production Unit/Railway Workshop after meeting the Railway's requirement and the Production Units Railway Workshops can undertake the work without detriment to their own or Railways work.

Note:

(i)        CWM (SAG) of Railway workshops may undertake such works, with the approval of associate finance of JAG level. However, Chief Workshop Managers (SAG) of Railway Workshops having Associate Finance Officers of the level of Senior Scale or below, may undertake such work with the approval of HQ's finance.

(ii)       This power may not be delegated by the Chief Mechanical Engineer of Production Unit/Coordinating HOD i.e. CWE/CWM of Railway Workshop to any authority subordinate to him but must be exercised by him personally.       

(iii)      The quotations should be given only to genuine buyers and those inquiries which are only for collecting market intelligence, should be avoided.

(iv)     All efforts must be made to secure best possible and most optimum price for Indian Rlys.          

(v)      While quoting the delivery schedule, Production Units/Railway Workshops will ensure that first the entire requirement of the Indian Railways is met and only the balance spare capacity is utilized for non-railway orders. Only such items should be undertaken which are normally used in Railway working.

 (vi)     The work should not be undertaken until after 10% of the estimated cost of the job,   viz. labour, stores, oncost (including proforma oncost) and all other charges leviable under the rules (paragraph 1426) and all other leviables have been deposited in advance by the party ordering the work, in case of manufacture of vehicles of Rolling Stock. In all other cases, 25% of the estimated cost of the job, as per the conditions indicated above, would be deposited by the party ordering the work. The balance payments regarding the work is to be deposited with the Railways as per the contract terms approved by the competent authority

(vii)    The work of charging batteries for wireless sets and motor cars belonging to Hospitals and Railway Institutes may be carried out where such facilities exist. 

(viii)    The term 'public bodies' for the purpose of this paragraph should be interpreted in its restricted sense to include organizations of a Semi-Government character as well as those sponsored or financed (partly or wholly) by the Central or State Government, for example Municipalities, District Boards, Corporations, Statutory Bodies, Commissions and Boards, etc., Political Social and Religious bodies should be excluded for this purpose.

1417A. DELETED

       All other existing provisions shall continue to apply.

(Authority:- Railway board's letter No. 2005/M(W)/964/97 dated 16.11.05 & 22.10.07) acs no. 4 & 6

1418. Estimates of work for other Government and Non-Government Railways asset Government Departments or Ministries.—In the case of works for other Government and Non-Government Railways and Government Departments or Ministries, the formal acceptance of the estimate and the estimated cost comprising of labour, material, shop oncost, general oncost, freight charges, storage, supervision, proforma oncost and profit leviable under the rules, should be obtained from the officers ordering the work before the work is put in hand. It should be made clear lo such officers that the estimates will be treated purely as estimates and that the actual cost of the work inclusive of Proforma oncost and profit as agreed to, will be realized. When work is undertaken for other Government Railways and Government Departments or Ministries, the estimate of the total outlay should also state the probable expenditure to be incurred during each financial year.

Note.—The work ordered by another Indian (Government) Railway can be put in hand, by the manufacturing Railway without obtaining the formal acceptance of the estimate provided the Chief Mechanical Engineer of the manufacturing Railway Workshop is satisfied-—

(a) about the availability of spare capacity in the workshop; and

(b) that the work to be done is of a really urgent nature.

This does not apply to work ordered by Non-Government Railways and other Government Departments or Ministries.

1419. Charges for Preparation of Estimates.—In the case of works, asked for by other Government or Non-Government Departments, private individuals or firms which are subsequently not carried out, and for which estimates have been prepared, charges should be recovered from the parties ordering the work, according to the following sliding scale, to meet the cost of preparing plans and estimates—

 

For works costing Rs. 1,00,000 and above

2 per cent on total estimated cost of work
For works costing Rs. 60,000 and above, but below Rs. 1,00,000 2 1/2  per cent
For works costing Rs. 30,000 and above, but below Rs. 60,000 3 per cent
For works costing Rs. 20,000 and above, but below Rs. 30,000 3 1/2 per cent
For works costing Rs. 10,000 and above, but below Rs. 20,000 4  per cent
For works costing Rs. 1,000 and above, but below Rs. 10,000 4 1/2  per cent

For works costing below Rs. 1,000 

5 per cent subject to minimum of Rs. 25


1420. The party concerned should be duly apprised in advance of its liability to meet the above charges and its acceptance thereof obtained before the work of preparation of estimates is taken in hand. In the case of local bodies and private individuals or films cash payment of such charges should be obtained in advance. The General Manager may, however, waive in any particular case, the levy of this charge subject to the conditions laid down in paragraph 1426.

INTEREST

1421. Interest during Construction from other Government Departments.—When capital expenditure is incurred on works constructed for use by another Department or Ministry, subject to interest and maintenance charges being recovered under the rules, interest on outlay on such works should be charged during the period of construction. The amount of interest charges recoverable should be calculated annually on the total capital outlay upto the end of the preceding year plus half the outlay for the year concerned. The rate of interest should be ruling rate of dividend as fixed. The whole of such amount recoverable from a particular department for any financial year should be adjusted in the books of the railway as a miscellaneous receipt under the major head "145 Indian Railway Commercial/ Strategic Lines Miscellaneous Receipts"

1422. Similarly, interest should be charged during the period of construction on the expenditure on works which are constructed by the Railway at the cost of another Department or Ministry to be handed over to that Department or Ministry after construction. Interest in such cases should be calculated on half the sum of the unadjusted outlay at the beginning and end of the year.

1423. The interest recoverable under paragraphs 1421 and 1422 above may, in the case of Company managed railways, be calculated monthly on the capital outlay up to the end of the previous month plus half the outlay of the month concerned, the whole of the amount recoverable from a particular department for any financial year being debited to that Department annually in one lump sum. In the case of certain railways managed by companies which pay interest on their capital half-yearly, the interest should be calculated half-yearly on the capital outlay upto the end of the preceding half-year plus half the outlay of the half-year concerned.

PRO FORMA ON COST

1424. All-in-cost of work executed in Workshops.—The "all-in-cost" of a work done in a Railway workshop is made up of the following elements:—

(a) Prime cost:—

(i). Cost of labour (ii) Cost of stores.

(b) Works oncost:

(i) Shop on cost (paragraph 706) Labour and stores } Added on the  basis of fixed  percentages on the cost paragraph 701)
(ii) General oncost (Paragraph 705) labour and stores

(c) Freight Charges.—The cost of stores under (a) (ii) and (b), freight charges en which have not been charged to the work, should be increased by 5 per cent to cover such charges (Paragraphs 2328 and 2727 of the Indian Railway Code for the Stores Department).

(d) Percentage charges on Stores.—Being 10 per cent on the total cost of stores, i,e,. stores under (a) and (b) above as increased by (c), to cover the cost of supervision, storage, &. c, and

(e) Pro Forma oncost—(Paragraph (703)

 (i) Supervision.

(ii) Provident Fund Contribution, Gratuity/ Special contribution to Provident Fund and other charges of works staff.

(iii) Repairs and Maintenance, 

(iv) Interest and Depreciation.

1425. Extent of Pro Forma Oncost leviable.—In framing estimates for work to be carried out in railway workshops, provision should be made for prime cost (Item (a) paragraph 1424) and 'Shop' and 'General' oncost (item (b), paragraph 1424) in all cases without exception, the other elements of cost being charged only to the extent indicated in the chart given below. The expenditure on "direct labour" likely to be incurred in each shop should, where possible, be shown separately and provision should be made for the inclusion of the shop oncost applicable to each such shop. 

Chart showing the charges to be levied on the cost of works executed in Railway Workshops 

For whom executed All-in-Cost
Prime Cost Works Oncost
Shops Oncost General Oncost Freight charges on the cost of stores (Col. 3 + 5+7)
Labour  Stores Labour  Stores Labour  Stores
1 2 3 4 5 6 7 8
Assumed figures and percentages:

(1) Government Railways :             (a) Ordinary Revenue or open Lane Works Revenue Development Fund upto New Minor Works Limited.

500

 

 

 

500

1000

 

 

 

1000

50% of (2)

 

 

       250

80% of (2)

 

 

 

400

40% of  (2)

 

 

         200

25% of (2)

 

 

 

125

5%

 

 

...

Chart showing the charges to be levied on the cost of works executed in Railway Workshops—(Contd.)

1 2 3 4 5 6 7 8
(b) Capital, Depreciation Reserve Fund, Development Fund (except New Minor Works) and Open Line Works Revenue (except New Minor Works) 500 1000 250 400 200 125 76
(2) Other state worked Railways and lines under construction by State 500 1000 250 400 200 125 76
(3) All other Railways } 500 1000 250 400 200 125 76
(4) Other Government Departments
(5) Private parties.
(6) Indian Auxiliary Force Corps connected with State 
worked railways
Same as for 3, 4 and 5 but if the cost of work done in shops does not exceed . Rs. 500, the charges leviable in the case of Home line employees (item 7 below) will only be recovered provided that no additional establishment is entertained for such work.
(7) Home line employees . 500 1000 250 400 200 125 76


For whom executed All-in-Cost
Pro Forma Oncost
Percentage on account of storage supervision etc (on cols 3+5+7& 8)
Supervisions (on cols ) 2+4+6  Provident fund contribution gratuity & other charges of works staff (on cols 2+4+6) Repairs & maintenance (on cols. 2+4+6) Interest and Depreciation (on cols 2+4+6)  Profit percentage (on cols 2 to 9) Total chargeable 


1 9 10 11 12 13 14 15
Assumed figures and percentages 10 % 60% 15% 10% 40% 10% ..
(1) Government Railways: . . . . . . .
(a) Ordinary Revenue or open Line Works Revenue Development Fund upto New Minor Works Limited. . . . . . . 2475
(b) Capital, Depreciation Reserve Fund, Development Fund (except New Minor Works) and Open Line Works Revenue (except New Minor Works) .. .. 143 95 380 .. 3169
(2) Other state worked Railways and lines under construction by State .. 570 143 95 380 .. 3739
(3) All other Railways } 160 570 143 95 380 271 4170
(4) Other Government Departments
(5) Private parties.
(6) Indian Auxiliary Forte Corps connected with State worked Railways. Same as for 3, 4 and 5 but if the cost of work done in shops does not exceed Rs. 500, the charges leviable in the case of Home line employees (item 7 below) will only be recovered provided that no additional establishment is entertained for such work.
(7) Home line employees 160 570 143 95 380 271 4170


*In the case of works or repairs, not exceeding Rs. 500 in cost, undertaken for any other railway, the charges in columns 9 to 14 may be remitted in reciprocation of a similar waiving of such changes by such railway.

Note 1— The charge for profit on work done in State-worked railway shops is 10 %. In the case of work done for other railways it may be foregone by mutual agreement, or may be levied at such higher or lower rate that 10 percent at which other Railway Administrations may agree to reciprocate.

Note 2 — The percentage charges on account of Proforma Oncost will be levied in the case of works chargeable to Capital and Depreciation Reserve Fund of the Home line only when the cost of the work done in shops exceeds Rs. 1000.

Note 3 —Percentage on account of freight charges (column 8) will not be levied on the value of such stores the cost of which is inclusive of such charges.

Note 4— In the case of stores manufactured for stock purposes, the same charges should be levied as in the case of home line revenue works.

Note 5 — The charges in column (14) will not be levied in the case of —

(i) Vehicles built for the Postal Department whether at the cost of that Department or at the cost of the Railway Department; and

(ii) Conversion of existing carriages into mail vans and vice versa and alterations in the dimensions of and changes in internal arrangements or fittings of postal vans.

Note 6 — The charges in column (14) will not be levied in the case of work done in connection with -he reserved carriages provided for officers of the Railway Police whether at the cost of the Provincial Governments concerned or the Railway Department.

Note 7 — The interest charges referred to in col. 13 above will be excluded in the case of works done under item 1 (b) of column above.


1426. Waiving of Proforma oncost and profit.—The General Manager is empowered to waive the recovery of Proforma Oncost and profit charges in respect of work done for outsiders or in the tendering for supplies called for by the Stores or other Departments. But such remission may be allowed wholly or in part by the General Manager only after consultation with the Financial Adviser and Chief Accounts Officer and for reasons that should be recorded. It should be examined whether the railway gains any advantage, financial or otherwise, by the remission and the fact that the Railway did not actually incur any identifiable overhead charges should not by itself be treated as a necessary and sufficient reason for foregoing the recovery of such oncost.

1427. No charges in respect of expenditure on ecclesiastical works should, under any circumstances be waived.

1428. Departmental charges on a Reciprocal Basis.—Notwithstanding the percentages mentioned in paragraph 1426 on account of Proforma Oncost and profit such charges may also be levied on a reciprocal basis to cover "the cost of tools and plant and establishment supervision" in case of works undertaken in Railway workshops for other Government Departments or Ministries, private railway companies or other public bodies (e.g., municipalities, trusts).

1429. Work done outside the Workshops.—The above rules (Paragraphs 1425 and 1426) apply to works done within the workshops. When works are executed outside the workshops, an addition of 12.5% only should be made on the total estimated outlay on labour and stores, to cover the cost of supervision &c.

1430. When a work is done partly inside the workshops and partly outside, the costs of these portions should be separately worked out and Proforma Oncost and profit levied only on the cost of the work done inside the shops and percentage charges mentioned in paragraph 1429 charged on the cost of work done outside the shops. 

SANCTION AND FUNDS .

1431. Sanction for Works to be executed in Workshops.—No works other than those of ordinary repairs and maintenance chargeable to Abstracts B and C may be undertaken in Indian Railway Workshops without the previous sanction of the General Manager or of an officer of the Mechanical Department to whom the General Manager may have delegated his powers in this respect, provided the rules in force from time to time relating to estimates and the provision of funds are observed.

1432. Funds for Home Line Revenue Works.—The outlay on works debatable to Abstracts B and C is met from the provision made in the "Authorization Rolls". For works chargeable to other Home Line Departments, the requisitioning Department is responsible for seeing that adequate sanction and funds exist for the works for which it indents. Information as to the probable cost of works should, if desired by the indenting departments, be furnished by the workshops. 

VERIFICATION OF ESTIMATES 

1433. One phase of the control of expenditure on Railways is a regular check by the Accounts Officer of all estimates before they are sanctioned by the competent authority. The object of this preliminary check of estimates is to avoid irregular sanction to expenditure and the main points which require consideration are— 

(1) the propriety of expenditure;

(2) the incidence and classification of charges;

(3) the existence of budget provision to meet the proposed expenditure during the financial year;

(4) the freedom from errors and omissions; and

(5) the competence of sanction.

The checks relating to these points should be exercised with reference to the rules in this Code and in other Indian Railway Cedes bearing on this matter.

1434. Propriety of Expenditure.—It is the duty of the Accounts Officer in, his capacity as Financial Adviser to examine zealously all proposals for expenditure, with a view to see—

(1) that the expenditure proposed to be charged to Railway funds in the estimate is properly and legitimately so chargeable; and

(2) that proper financial justification is forthcoming in the case of all works requiring such financial justification.

1435. Incidence and Classification of Charges.— These should be verified in an estimate in accordance with the rules of incidence and the classification of expenditure prescribed in the Indian Railway Financial Code. In his verification certificate, the Accounts Officer should clearly state that incidence and allocation have been so verified.

1436. The submission of an estimate to the sanctioning authority should not be delayed when there arises any doubt as to the correct allocation of the estimated cost and the question at issue will take time to settle. In such cases, the approximate allocation between Capital, Depreciation Reserve Fund, Development Fund. Open Line Works- Revenue and Ordinary Revenue may be certified by the Accounts Officer, as far as it is possible for him to do so, and the sanctioning authority may sanction the estimate, if otherwise in order, leaving over the question of final allocation for subsequent consideration.

1437. The existence of Budget Provision.—For a proposed work should be verified from the sanctioned budget statements for the year.

1438. Errors and Omissions.—Noted in the course of Accounts verification of estimates, it any, should be got corrected by the Executive Authority responsible for the preparation of (or sanction to) the estimates. The Accounts Officer may, in cases where this becomes necessary, append to his verification certificate, a note specifying such items of errors or omissions as have been pointed out by him, but have not been accepted by the Executive Authority and any other matters of importance.

1439. Competency of Sanction.—This should be verified with reference to the limitations laid down in the schedule of powers of various authorities (Annexure II to Chapter V of Financial Code, Vol. I). The rule regarding grouping of works for the purpose of determining the authority competent to sanction an estimate is given in paragraph 750 of the Indian Railway Code for the Engineering Department.

1440. Subsidiary Points to be checked.—In the check of estimate the following subsidiary points require attention. It should be seen—

(1) that the particulars of work to be done are furnished in sufficient detail and that a proper distribution is made of the estimated outlay between cash and Stores-.

(2) that the allocation of each item is given and that;

(3) that all incidental expenditure that can be foreseen has been provided for in the estimate;

(4) that in the case of renewal, replacement and dismantlement works, credit for sale proceeds of released material has been provided for;

(5) that in the case of work to be done for other Government Departments or Ministries, Non-Government railway and private bodies, provision has been made for the necessary additional charges as laid down in paragraph 1426;

(6) that in the case of estimates for manufacturing operations the outlay and out-turn are distinctly shown;

(7) that estimates are prepared for material released from stock condemned or broken up without replacement; and

(8) that in the case of revised estimates, a statement comparing the figures with previous sanctioned estimates and containing explanations for variations accompanies the revised estimate.

1441. Certificate of Accounts Verification.—All estimates verified by the Accounts Officer should bear a certificate of such verification. The form of the certificate may be as under:—

"Incidence and allocation verified (subject to the check note attached). This requires the sanction of............"

1442. A copy of the estimate as verified by the Accounts Officer, together with a verbatim copy of his check note, if any, should be submitted to the authority competent to sanction the estimate. In forwarding an estimate for sanction, it should be clearly mentioned whether it has been accepted by the Accounts

Officer as unobjectionable. In cases where the Accounts Officer has recorded any objection, the attention of the sanctioning authority should be drawn to the Accounts Officer's check note stating the objection.

1443. Estimate Register.—Details of all estimates received in the Workshop Accounts Office for verification should be recorded in this Register (W. 1443) and all entries should be attested by Section Officer (Accounts). 

Form W. 1443 

ESTIMATE REGISTER

S. No. Estimate Name of work Estimated cost Chargeable
No. Dt. Capital Depre ciation Reserve Fund Develop ment Fund Open  Line  Works
Ordinary Revenue
1 2 3 4 5 6 7 8 9 10

 

Date of receipt Date of return after verification Reference to sanction Remarks
Authority sanctioning the estimate No. Date
11 12 13 14 15 16

1444. Sanction to Estimates.—Advice of all sanctions to estimates by the competent authorities should be communicated to the Accounts Officer and to the Chief Auditor of the Railway in such form as may be prescribed by such authorities. A copy of the sanctioned estimate should also be furnished to the Accounts Officer.

1445. Currency of Sanction.—The sanction to an estimate will ordinarily remain current for five years from the date on which it has been accorded, unless it has been renewed for a further term by the acceptance of a revised estimate. Acceptance by competent authority however, of a budget estimate which includes specific provision for expenditure on a work which is in progress may be regarded as reviving for the year in which provision is made, the sanction to the estimate—regardless of the five years limit. But if no work has been commenced on a sanctioned estimate within two years of the date on which the sanction was accorded, such sanction should be held to have lapsed and fresh sanction should be obtained from the competent authority by the submission, of an up-to-date estimate, if necessary.

1446. The currency of sanction begins from the date of sanction to the estimate itself and not from the date on which the allocation of the estimate is finally accepted. Incidence of Cost of Works Done for other Departments/Ministries

Postal Vans

1447. The following rules govern the incidence of the cost of vehicles or parts of vehicles provided by the Railway for the Postal Department,

1448. The capital cost of newly built vehicles expressly constructed for the exclusive use of the Postal Department on their requisition for complete vehicles, shall be paid by that Department. Should the Railway find it necessary to construct new vehicles to meet the requisition of the Postal Department for parts of vehicles, no portion of the capital cost shall be charged to that detainment which shall only pay interest on the capital cast of such vehicles.

1449. When a postal vehicle built at the cost of the Railway Department is replaced entirely, the cost of the new vehicle should be treated as a recovery of interest charges.

1450. In the case of mail vans rebuilt with old reconditioned under-frames, etc., interest charges on the second-hand under frames and bogie- trucks should be calculated at the rate of interest which was in force at the time the under frames were constructed and the interest on the cost of new bodies should be charged at the current rate of interest.

1451 (1) The following should be the minimum standards for equipment in the Postal portion of the coaching stock.: - 

(i) The battery and dynamo should be designed for service in the vehicle only and not to augment the units in the Block Rake.

(ii) All Postal vehicles having a connected load greater that 10 amps should be fitted with dynamo and battery.

(2) The following standards for lights and fans should be adopted as minimum requirements: —

Letting; (1) 65/110 Lux (metric candle;.) over Sorting Ledge and Registration and Pared Ledges

(ii) 45/65 Lux (metric candles) over other places. Fans—

(iii) Fans 2—16" standard carriage fan per 100 square feet of floor area.

(3) The Capital cost of electric battery, dynamos, switchgear and wiring should be divided between the Postal and Railway Departments in the proportion that the connected load in the Postal portion bears to the total connected load of the vehicle.

(4) The above procedure should be given effect to subject to the following reservations: —

Paragraph (1) (i) and (ii) is obligatory when in future new vehicles with Postal accommodation are constructed or rebuilt. Paragraph (2) is accepted as desirable on all existing stock and obligatory on all future stock, the existing stock being brought at least up to this standard as and when Postal vehicles pass through shops for periodical overhaul.

Paragraph (3) should be accepted for future construction and adopted for existing stock which is equipped with generator and batteries and is not wired for use in block rakes. For vehicles which are wired for use in block rakes the ruling applies on the specific understanding that the charges to the Postal Department shall not be increased.

Note: In the case of partially fitted Postal vehicles where the dynamo and battery equipment ate specially provided for the exclusive use of the Postal portion of the vehicle, the remainder of vehicle being wired as part of the block rake and being entirely distinct from the Postal portion, the entire cost of the equipment shall be included in the capita! cost of the Postal portion for the purpose of recovery of interest charges for the Postal Department

1452. When existing vehicles which have, on the requisition of the Postal Department, to be converted as completed vehicles or parts of vehicles to meet the requirements of that department, they shall pay—

(i) the cost of alteration, together with the cost of transporting such vehicles to workshops for alterations and from workshops to the station at which requited after alteration, where the vehicles have to be transported on trucks due to gauge difference; and

(ii) interest on the capital cost of the complete vehicles or parts of vehicles, so long as they remain in the exclusive use of, and have not been formally surrendered by the Postal Department.

1453. The capital cost of postal vans referred to in the preceding paragraphs will, for the purpose of levying interest, be the all in cost as detailed in paragraph 1424. The capital cost of the postal portion of the non-postal vehicles will be worked out in proportion to the floor area of the postal portion, the 'all-in-cost' of any special fittings provided in the vehicle for the exclusive use of the postal Department being added to proportionate cost of the postal portion as thus worked out.

Note: The postal portion of a non-Postal vehicle is that portion of the accommodation in a railway coaching vehicle which is reserved for the conveyance of mails.

1454. When Postal Department formally surrenders vehicle or parts of vehicles, the capital cost of which has not been paid by that department, they shall pay to the Railway Administration the cost of converting such vehicles or parts of vehicles so as to render them serviceable for general traffic purposes, together with the cost of transporting such vehicles to workshops for conversion and from workshops to the station at which required after conversion, where the vehicles have to be transported on trucks due to gauge difference.

1455. When the Postal Department formally surrenders complete vehicles or parts of vehicles, of which it has paid the capital cost, the Railway Administration shall refund to the Postal Department this sum less the cost of any special fittings, that would be valueless and also less the cost of converting such vehicles for general traffic purposes.

Saloon Carriages and other vehicles reserved for the exclusive use of Departments/ Ministries of Government of India and State Governments.

1456. The following rules apply to vehicles reserved for the exclusive use of State Governments or of  Departments /Ministries of the Government of India excluding vehicles reserved for the Railways and the Railway Police.

1457. The vehicles, together with their electrical and movable equipment and furniture, will be provided at the cost of the Railways. The capital cost of a vehicle and its equipment will be known as "The capital cost of the vehicle on the books of the railway" and will be the all-in-cost as defined in paragraph 1424.

1458. The Department/Ministry of State Government will be responsible for obtaining the prior sanction of the competent authority to the provision of any reserved vehicle.

1459. Design of all stock should be to the standards laid down for rolling stock on Indian Railways and must receive the prior approval of the Railway Board.

1460. The Department/Ministry or State Government will pay the following charges for each vehicle annually to the Railways: —

(i) interest at 4.5 per cent per annum, on the capital cost of the vehicle on the books of the railway;

(ii) depreciation at the rate of one per cent per annum on the capital cost of the vehicle on the books of the Railway. Depreciation will not be charged on any vehicles after it has been m use for 40 years;

(iii) an all-round charge of 4% per annum on the capital cost of the vehicle on the books of the railway or the present day cost of construction of a new similar vehicle, whichever is greater, to cover charges for maintenance and repairs of the vehicle and its equipment; and

Note: This has effect from 1st November, 1952 in respect of all cases except Military Cars in regard to which it takes effect from the 1st April, 1953.

(iv) haulage at the prescribed scheduled rates, which will not include any recurring charge for interest depreciation or maintenance and repairs.

1461. When any alterations or additions to the body of a vehicle or any alterations or additions to the equipment, fittings, or furniture are carried out at-the request of the using Department/Ministry or State Government, the Department/Ministry or State Government will pay the actual cost of such alteration or addition. Such alteration or addition will only be carried out when previous sanction has been given to an estimate of the actual cost by the competent sanctioning authority, and when the authority at whose cost the alterations or additions are to be carried out, has undertaken to defray its actual cost.

1462. Where vehicles of special design or of special equipment are provided as a temporary measure for the exclusive use of a Department/Ministry or State Government, the Department/Ministry or State Government concerned will pay the actual cost of Converting the stock for ordinary railway purposes.

Note: This also covers the stock permanently built for Defence Ministry, which has still as portion of its normal life to run and is surrendered by the Ministry of Defence.

1463. When it becomes necessary to replace vehicles, or equipment, etc. new stock or equipment, etc. will be provided at the expense of the Railways. Should replacement of a vehicle be required by the using Department /Ministry or State Government while it is still in good condition and before the expiry of its assumed normal life, namely, 40 years, the using Department/Ministry or State Government will be required to pay the Railway the actual cost of converting the replaced vehicle for use as ordinary stock.

1464. The actual cost of work referred to in the preceding three paragraphs includes the charges detailed in paragraph 1424, less credit for the depreciated value of all material or equipment released.

1465. When a new vehicle has been built in replacement of an existing one, the interest, depreciation and maintenance and repairs charges to be paid annually on the new vehicle will be calculated in accordance with clauses (i) to (iii) of paragraph 1460 on the actual cost of replacement.

1466. A proforma Capital and Revenue Account should be kept for all such vehicles to see that the recoveries made from the various Departments/Ministries of the Government of India and State Governments on account of interest, maintenance and depreciation do not fall short of the actual expenditure incurred by the railway One account should be kept for all the vehicles, but a separate account for individual vehicles may be considered necessary where there is reasonable doubt that the financial interests of the railway are adversely affected.

The Capital Account should show the capital cost of the saloons, the accuracy of which should be checked by the Accounts Officers. The Revenue Account should indicate the expenditure incurred from year to year by the railway; whether in the workshops or on the line, on the maintenance and repairs of the vehicles. The expenditure on empty haulage in connection with periodical overhauled and trial runs incidental to the maintenance of these vehicles should also be included in the Revenue Account. 

Execution of Works 

1467. All works should be carried on as rapidly as is possible, due regard being had to the extent of funds allotted and to soundness of execution. The general rule in regard to the building of rolling stock is that all stock should be built to designs approved by the Board. In cases where it is proposed to build stock to new designs, no indents for the necessary materials should be allowed to go forward, nor should any work be taken in hand until the approval of the Railway Board has been obtained to the new designs. In the case of Coaching Stock, however, all designs, whether already sanctioned by the Railway Board or new ones, should be submitted for the prior approval of the Board and no indents for materials should be allowed to go forward, nor should any work be taken in hand, until such prior approval has been obtained. 

B. Completion Reports 

1468. All delays in the advice of date of completion by the Mechanical Department should be regularly taken up. The works on which no expenditure is incurred for three consecutive months should be specially brought to the notice of the Mechanical Department and that Department should be asked to intimate whether the work has been completed and when a completion advice may be expected.

1469. Completion Reports.—As soon as the advice of completion is received (Paragraph 835) the clerk who maintains the Works Register should prepare a Completion Report in Form No. W. 1469. The figures of actual expenditure as well as those of estimated amount should be shown in the same details in which the estimate has been prepared and sanctioned, but before preparing the Completion Report it should be seen that (I) all charges under different sub-heads of estimate have been booked, and (2) the credit for released material has been adjusted. 

Form W. 1469 

.....................................Workshops

No............................................................                                                                Date........................
Completion Report of..................................................................................

................................................................................................................

................................................................................................................

Authority.............................................Estimate No.. ...............................of......................................

Name of Office in charge of the work...................................................................................................

When commenced.............................................................................................................................

When completed...................................................................................................................................

Sub-heads of estimate As estimated As executed Difference Remarks
Quantity Number Amount Quantity Number Amount Excess (+) Saving (-)
1 2 3 4 5 6 7 8

Explanations for vitiations shown in columns in 6 and 7 above. 

Dy. Chief Mechanical Engineer 

1470. The Completion Report should be submitted to the authority competent to sanction the excess, after scrutinizing the explanation regarding excesses over estimates obtained from the Works Manager or the Deputy Chief Mechanical Engineer, as the case may be. Completion Reports which do not show any excess over the estimate should be filed after obtaining the explanation for the saving, if any, from the Works Manager or the Deputy Chief Mechanical 
Engineer and after endorsement of a certificate of verification thereon Saving of over 15 per cent should be reported to the Chief Mechanical Engineer.

1471. Completion Report Register.—The Accounts Office should watch through a register (W. 1473) that the completion reports involving excesses over sanctioned estimates are received back duly sanctioned from the authority competent to sanction the excess,

1472. A note should also be recorded in the Works Register under the work concerned in the following form—

"Work completed and completion report prepared and submitted to .................. on ............ for sanction.

1473. All completion reports should be entered in the Completion Report Register. This register shows the following details: —

(1) Serial Number.

(2) Date of submission.

(3) Particulars of work.

(4) Estimated cost.

(5) Booked expenditure.

(6) Reference to works register.

(7) Department.

(8) Work order number.

(9) Reference to sanction to the excess, where necessary.

(10) Remarks.

1474. Adjustment of charges and Credits reported on completed works.—The following procedure should be followed in cases of charges and credits reported on completed Works necessitating the revision of Completion Reports—

(1) If charges or credits are received for a work after the submission of a Completion Report not yet sanctioned, a revised Completion Report should be prepared and necessary postings should be made in the Works Register against the work concerned.

(2) If charges or credits are received after sanction to the completion report for the work, charges not exceeding Rs. 10,000 should be adjusted against the appropriate head of account under Ordinary Revenue Maintenance and credits not exceeding Rs. 10,000 against abstract Z. 650. When charges or credits exceed Rs. 10,000, the account of the work should be re-opened and necessary adjustment made thereunder. In the case of works done for private parties or other Government Departments or Ministries, the actual amount spent on the work should be recovered even though the completion report may not be revised.