About Indian Railways
   Corporate Overview
      Directorates
         Civil Engineering
            SANCTION LETTERS
               ORI-2007


 
Bookmark Mail this page Print this page
QUICK LINKS
ORI-2007

 

ORI-2007

S.No

File No.

Date

Subject

1

2005/CEDO/ORI/22

20.12.2007

Opening of newly converted BG line from Gosaigaonhat to Fakiragram section (23 kms) in Alipurduar Division of N.F. Railway.

2.

2001/CEDO/ORI/18

20.12.2007

Opening of BG electrified UP & DN main Double line between Chitoda Jn. Cabin and Sewagram station in Nagpur Division of Central Railway.

3.

2004/CEDO/ORI/2

20.12.2007

Opening of existing alignment after regarding between Km. 20/3- 23/6 and constructing 3 x 18 m + 2 x 12.8 m span bridges for Narmada main canal at Km. 221/10-11 on Kalol – Katosan Road MG section of Rajkot Division on Western Railway.

4.

2000/CEDO/ORI/46

20.12.2007

Opening of the new BG line between stations Goalpara Town and Kamakhya in Alipurduar Division of N.F. Railway.

5.

98/CEDO/ORI/11

20.12.2007

Opening of newly converted BG line between Sripuriagaon and New Tinsukia Bye –Pass Line (3.49 Kms.) in Tinsukia Division on N.F. Railway.

6.

2001/CEDO/ORI/26

20.12.2007

Opening of the new railway line between Panihar and Mohana stations in Jhansi Division on Central Railway (presently in N.C. Railway).

7.

99/CEDO/ORI/11

19.12.2007

Opening of the new BG double line between Kasargod – Kumbla and Uppala- Kumbla stations of Palghat Division on Southern Railway.

8.

2005/CEDO/ORI/13

26.11.2007

Opening of newly converted BG line from Viramgam-Mahesana stations of Ahmedabad Division on Western Railway.

9.

1999/CEDO/ORI/24

26.11.2007

Opening of BG converted line from MG between Indara Jn. to Phephana Jn. stations of Varansi Division on N.E. Railway.

10.

1999/CEDO/ORI/25

26.11.2007

Opening of BG converted line from MG between Gorakhpur Cantt. to Gorakhpur Jn. stations of Lucknow Division on N.E. Railway.

11.

2000/CEDO/ORI/4

26.11.2007

Patch doubling Between Kalisindh-Bolai stations from Km. 126.881 to Km. 133.199 (New Km 133.164 BLX) on Ujjain-Bhopal section on Western Railway.

12.

2003/CEDO/ORI/5

26.11.2007

Opening of new BG line for Public Carriage of Passengers between Maksi- Dewas new BG sections to a length of 36.036 Kms. (from Km. 0.00 to 36.036) of Ratlam Division on Western Railway.

13.

2000/CEDO/ORI/14

26.11.2007

Existing alignment after Re-grading between Km. 393/8 & 396/3 after constructing 6 x 18.3 m span bridge for Narmada main Canal at Km 394/10-11 on Ahmedabad- Himmat Nagar (MG) section of Rajkot Division on Western Railway.

14.

2000/CEDO/ORI/8

15.11.2007

Permanent Diversion of main line between Km. 56/6 & 62/4 for construction of main canal crossing R (5) at. Km. 60/400 on Anand- Godhra (BG) section on Vadodara Division on Western Railway.

15.

96/CEDO/ORI/32

07.11.2007

Commissioning of Makrana- Parbatsar newly converted BG line on Jodhpur Division of North Western Railway.

16.

2000/CEDO/ORI/20

24.10.2007

Restoration of Bye Pass line between Joonathpur and Vyas Nagar station on the Northern Railway.

17.

2000/CEDO/ORI/18

24.10.2007

New double line between Jind & Barsola stations on Delhi- Bhatinda section of the Northern Railway.

18.

2000/CEDO/ORI/17

24.10.2007

Commissioning of Beas- Goindwal newly constructed B.G. line on Firozpur Division of the Northern Railway.

19.

2001/CEDO/ORI/33

24.10.2007

Opening of doubling line between Pichkurir Dhal and Bhedia stations of Hawrah Division in Khana- Sainthia section of Eastern Railway.

20.

2001/CEDO/ORI/43

24.10.2007

Opening of converted B.G.  line between Wankaner- Dahisara section of Rajkot Division on Western Railway.

21.

2001/CEDO/ORI/17

10.10.2007

Opening of the Patch doubling between Kalisindh- Berecha stations for passenger traffic from Km. 126.946 to Km. 115.07 (New Km. 11.876) on Ujjain – Bhopal section of Western Railway.

22.

2001/CEDO/ORI/21

05.10.2007

Opening of Permanent Diversion to passenger traffic between Km. 766/8 to Km. 769/5 (2.752 Km.) on Ahmedabad – Mehsana Bg/MG section in connection with Narmada main canal crossing R-10 at Km. 767/6-7 between Khodiyar – Kalol.

23.

2001/CEDO/ORI/46

05.10.2007

Opening of Railway- Doubling BG- DN/UP line in Kanki – Surajakamal – Dolkolha section (14.53 Km.) of New Jalpaiguri- Malda Town BG main line of Katihar Division of N.F. Railway.

24.

1996/CEDO/ORI/23

10.09.2007

Opening of the newly BG double line between Sasthanketta – Quilon on Ernakulam- Quilon section of Trivandrum Division of Southern Railway.

25.

2007/CEDO/ORI/45

30.08.2007

Opening new 3rd BG main line including introduction of 25 KV AC Traction between Allahabad station and Subedarganj station of Allahabad Division of North Central Southern Railway.

26.

2006/CEDO/ORI/10

24.08.2007

Opening of newly converted BG railway line of 47.973 Kms. Between Madurai Jn. (incl.) and Manamadurai Jn. (incl.) stations of Madurai Jn. – Rameswaram section in Madurai Division of Southern Railway.

27.

1998/CEDO/ORI/10

16.08.2007

Opening of BG single line- Netravati Bye pass 1020 m length connecting Shoranur- Mangalore line with Mangalore – Merambur line on Palghat Division of Southern Railway.

28.

2002/CEDO/ORI/4

30.07.2007

Opening of newly converted BG railway line from Makum Jn. to Dangari of Tinsukia Division of N.F. Railway.

29.

2004/CEDO/ORI/24

27.07.2007

Opening of newly converted BG railway line between Rajkot- Junagarh section to a length of 103.01 Kms. (from Kms. 0.00 to 103.01) of Rajkot and Bhavnagar Divisions of Western Railway.

30.

2006/CEDO/ORI/22

18.07.2007

Conversion of 1500 V DC Traction to 25 KV AC Traction in Kasara- Igatpuri section of Central Railway.

31.

2004/CEDO/ORI/66

17.07.2007

Opening of Gauge conversion between Virudhunagar and Tenkasi section- opening of the converted main line between Rajapalayam (excl.) and Tenkasi (incl.) station (from 591.174 to Km. 660.478 for a length of 69.304 Km.) for public carriage of Passengers.

32.

2002/CEDO/ORI/11

29.06.2007

Opening of newly converted BG line between Amguri Jn. to Tuli station on Tinsukia Division of N.F. Railway.

33.

2004/CEDO/ORI/16

27.06.2007

Opening of Gauge conversion between Subrahmanya Road (incl.)- Kabkaputtur (excl.) stations in Ariskere-Hasan-Manglore Gauge conversion project of Mysore Division of South Western Railway.

34.

2000/CEDO/ORI/3

26.06.2007

Permanent diversion of the down main line between Km. 440/26 and 443/14 for construction of main canal crossing R(4) at Km. 442/278 on Vadodara – Godhra (BG) section of Vadodara Division of Western Railway.

35.

2006/CEDO/ORI/2

19.01.2007

Opening of newly converted BG line between Sihor Jn. – Palitana stations of Bhavnagar Division of Western Railway.




Source : Ministry of Railways (Railway Board) CMS Team Last Reviewed on: 02-06-2011  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2010  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.